What are BSUoS charges?
BSUoS, Balancing Services Use of System, is the charge that recovers what the National Energy System Operator spends keeping electricity supply and demand matched in real time. Since 1 April 2023 it has been a single national tariff, fixed in advance and recovered from electricity demand only. For settlement days from 1 April to 30 September 2026 it is £13.74 per MWh, which is 1.374p per kWh.
It has no zones, no time bands and nothing to negotiate. Because the rate is published months ahead of the period it applies to, the BSUoS line on an invoice can be reproduced exactly rather than taken on trust.
- Per MWh, April to September 2026
- £13.74
- Fixed Tariff 7, published as final by NESO on 29 December 2025. The same figure is 1.374p per kWh.
- Per MWh, October 2026 to March 2027
- £12.49
- Fixed Tariff 8, published on the same day. The rate steps down by £1.25 per MWh at midnight on 1 October 2026.
- Minimum notice of a price
- 3 months
- Users are given at least three months notice of the Fixed BSUoS Price for the next fixed price period, under CUSC paragraph 14.31.8.
What BSUoS pays for
Electricity has to be generated in the same instant it is used. Wholesale contracts get the country close, and then somebody closes the gap for every half hour of every day: paying a generator to turn up when demand comes in higher than the market expected, paying one to turn down when the wind blows harder than forecast, holding reserve, managing voltage and frequency, and working around network constraints. That is the balancing job, and Balancing Services Use of System is how it is paid for.
The costs it recovers are listed in Section 14 of the Connection and Use of System Code, the contractual framework for using the national transmission system. In plain terms they are:
- The Balancing Mechanism. What NESO pays generators and large users to change what they were going to do, in each half hour. The same accepted actions are what the imbalance price for that half hour is calculated from.
- Balancing services contracts. Reserve, response, inertia, voltage and restoration services bought ahead of time rather than in the moment, plus the cost of contracting for and developing them.
- Internal expenditure and returns. What it costs to run the system operator itself, and the return on its regulated asset value, both as defined in its licence.
- Adjustments. Corrections for prior years, manifest errors, special provisions, and costs under contracts awarded through the onshore tender process.
The scale is worth stating, because it explains why a charge nobody negotiates moves as much as it does. For the six months from April to September 2026, NESO forecast balancing costs of £1,285.2 million and internal costs of £400.0 million. After a negative recovery adjustment of £69.8 million and £6.1 million of other credits, the total to recover across those six months is £1,609.3 million.
Who pays it, and who does not
This is the part that has changed most, and the part most published explanations still get wrong. Until 1 April 2023, BSUoS was recovered from generation and demand together. Ofgem approved CUSC modification CMP308 on 25 April 2022, and from the start of the 2023/24 charging year the charge moved onto final demand only. Final demand means electricity consumed for any purpose other than generation or export onto the network.
| Party | Liable | Basis |
|---|---|---|
| Suppliers, for the demand they settle | Yes | The Fixed BSUoS Price for the settlement day, applied to the gross demand volume of the supplier BM Unit in every settlement period of that day. |
| Directly connected transmission demand | Yes | The same price, applied to the metered volume of the transmission connected BM Unit. |
| Generators | No | Removed by CMP308 with effect from 1 April 2023. |
| Interconnector BM Units | No | Not liable under CUSC paragraph 14.31.14, including those of the Interconnector Error Administrator. |
| BM Units of Virtual Lead Parties | No | Not liable under the same paragraph, including secondary BM Units. |
You are not a party to the CUSC, so NESO never invoices you. It invoices your supplier for the demand your supplier settles, and your supplier recovers it from you. How visible that is depends entirely on the contract. On a pass-through contract BSUoS is billed at cost as a line of its own, or inside a combined non-commodity line. On a fully fixed contract it is inside the unit rate at a level the supplier guessed at, and priced a risk premium for, when the contract was signed.
How the tariff is set
Before April 2023 BSUoS changed every half hour and was only known after the event, which made it impossible to budget for and impossible to hedge. The Second BSUoS Task Force recommended fixing it. Ofgem approved CMP361, with the consequential CMP362, on 15 December 2022, and from 1 April 2023 the charge became an ex-ante fixed tariff: set in advance, the same for every settlement day in its period, and deliberately without a fund standing behind the tariff to smooth it. Two balances do exist, and they matter for one thing only, which is the mid-period reset described below.
Two further modifications, CMP408 and CMP415, were approved on 30 October 2024 and implemented on 1 April 2025. Together they shortened the notice period from nine months to three and lengthened the fixed price period from six months to twelve, which sounds contradictory until you see the shape it produces: NESO now sets a whole charging year at once, as two seasonal tariffs running April to September and October to March, giving a combined fifteen month framework. Fixed Tariffs 7 and 8 are the first pair published under it.
- JuneInitial forecast→
A first view of both tariffs for the charging year starting the following April. Indicative only, and it has moved by December every year so far.
- SeptemberDraft tariffs→
The forecast rebuilt on later cost and volume data, published for industry to respond to. This is the committed month rather than the outturn: the first draft under the new timetable landed on 2 October 2025.
- By 31 DecemberFinal tariffs→
Both become the Fixed BSUoS Price. The second is known nine months before it applies.
- 1 April and 1 OctoberThe price steps
The new tariff applies from the first settlement day of the period, with no transition across the boundary.
The tariff itself is the forecast total cost divided by the forecast volume it will be spread over. What lands on your invoice is that tariff applied to your volume, for each settlement day.
The published tariff, in pounds per MWh, for the fixed price period the settlement day falls in. £13.74 for 1 April to 30 September 2026, £12.49 for 1 October 2026 to 31 March 2027.
The volume settled for the BM Unit, in MWh, summed across every settlement period in the day. The code measures it at the transmission system boundary and multiplies it by the transmission loss multiplier, so it is not the reading on your meter.
The number in the first term is produced by dividing forecast total BSUoS costs by the forecast of transmission connected and gross demand volume for the period. For April to September 2026 that is £1,609.3 million over a forecast 117.10 TWh, which gives £13.74 per MWh. For October to March it is £1,812.0 million over 145.04 TWh, or £12.49. Both were struck against forward price curves averaged over the first week of December 2025.
What it costs, worked through
Start with the case that has no complications: a billing period sitting wholly inside one fixed price period. The consumption below is an assumption, clearly labelled as one. The rate is not.
- Consumption assumed, August 2026
- 250,000 kWh
- Converted to MWh
- 250 MWh
- Fixed Tariff 7, 1 April to 30 September 2026
- £13.74 per MWh
- 250 × 13.74
- £3,435.00
Now the case that catches people out, and the single most common way a BSUoS line is wrong: a period that crosses a tariff boundary. Take the same site on a monthly cycle that runs from 16 September to 15 October 2026.
- Billing period assumed
- 16 Sep to 15 Oct 2026, 30 days
- Consumption assumed, spread evenly
- 30,000 kWh
- 15 days at Fixed Tariff 7, 15 MWh × £13.74
- £206.10
- 15 days at Fixed Tariff 8, 15 MWh × £12.49
- £187.35
- Total for the period
- £393.45
Price the whole thirty thousand units at Fixed Tariff 7 and the line reads £412.20, an overcharge of £18.75 on one meter for one month. That is small enough to sit inside most tolerances and large enough to be worth several thousand pounds a year across a portfolio of a hundred meters, twice a year, every year.
Where it appears on your invoice
There is no standard line name. The same charge arrives under at least five different headings depending on the supplier, and one of them is not a heading at all.
| What the line says | What it means | Can it be checked on its own |
|---|---|---|
| BSUoS | The charge itself, usually as pence per kWh against the period volume. | Yes |
| Balancing Services Use of System | The same thing, spelled out. Some suppliers add the tariff number. | Yes |
| Balancing services, or Balancing charges | Almost always BSUoS. Occasionally it also carries Elexon and settlement costs, which are a different charge. | Only if the invoice says what is in it |
| BSUoS reconciliation, or a BSUoS line for an old period | A final reconciliation charge or credit, around fourteen months after the settlement day. | Yes, against the tariff for the period reconciled |
| Third party costs, or Non-commodity charges | BSUoS bundled with transmission, distribution and the policy levies into one number. | No. Only the total can be checked, so an error in one component hides under an error in another |
If the line is bundled, you can ask your supplier in writing for the breakdown. That is worth doing before you need it rather than after, and for a business claiming network charge compensation it is not optional: obtaining the detail is explicitly the responsibility of the applicant, as the EII exemption guide sets out.
How to check it
BSUoS is the easiest large pass-through charge to verify, because there is exactly one rate in play and it is published. Five questions settle it, in this order.
- Does the period cross 1 April or 1 October? If it does, the line should be the sum of two calculations, not one. Look here first, because it invalidates everything after it.
- Is the rate the published one? Not the rate in the contract, and not last period. The Fixed BSUoS Price for the settlement days actually billed.
- Are the units consistent? NESO publishes in pounds per MWh and most suppliers bill in pence per kWh. Divide by ten, and check you have not divided twice.
- Is the volume the one the charge applies to? Gross demand volume at the boundary, not metered units. A line that matches your meter reading exactly may be the one that is wrong.
- Is this an original charge or a reconciliation? An amount for a period you have already paid for is normal. Price it against the tariff for the period reconciled, not the current one.
What is changing
The rate falls on 1 October 2026
Fixed Tariff 8 is £12.49 per MWh against Fixed Tariff 7 at £13.74, a fall of £1.25 per MWh or 9.1%. On a site consuming 250,000 kWh in a month that is £312.50 less. Both figures were published together on 29 December 2025, so a supplier has had nine months notice of the second and there is no excuse for an invoice that misses the step.
The pair before them ran the other way. Fixed Tariff 5 was £10.74 per MWh for April to September 2025 and Fixed Tariff 6 was £15.69 for the winter half, a rise of 46%. A charge that jumps 46% in one step and falls 9% in the next is not a number to carry forward from the budget you set last year, and the fixed tariff regime removed the volatility within a period without removing it between periods.
Tariffs 9 and 10 arrive by the end of December
The initial forecast for the 2027/28 pair was due in June 2026 and the draft in September 2026, with the final figures published by 31 December 2026. Until then nothing about April 2027 is fixed, and a forecast tariff is not a tariff.
Billing gross rather than net is under challenge
CMP453, raised on 30 April 2025, would bill BSUoS on a net basis at BSC Trading Units. Under gross billing a customer inside a trading unit pays BSUoS even where the net flow at the point of connection is an export, which is to say even where they are not using the system. The final modification report of 11 November 2025 asked for implementation on 1 April 2026 and for a decision by 30 November 2025. Neither happened: Ofgem lists CMP453 as a decision still pending, with a decision date of 30 September 2026. It matters most to sites with significant on-site generation.
Deep dives and edge cases
The main path above covers a BSUoS line on a current invoice. These are the cases that come up often enough to answer and not often enough to interrupt it.
Before April 2023 the rate changed every half hourWhy a historic reconciliation cannot be checked with a single number.+
For every settlement day up to the end of March 2023, BSUoS was settled per settlement period: forty-eight rates on a normal day, forty-six or fifty on the two clock-change days a year, and some of them negative, because balancing occasionally earns money rather than costing it.
Checking such a period means joining every half hour of consumption to the rate published for that exact date and settlement period, and summing. An average rate is an approximation, and on a peaky demand shape not a small one. NESO still publishes those rates by settlement period.
A tariff can be reset part way through its periodThe escape hatch in the CUSC, and the five days of notice it carries.+
The tariff is fixed, but not unconditionally. Under CUSC paragraph 14.31.15, if NESO forecasts that it will neither recover enough through BSUoS charges nor hold enough in the Industry BSUoS Fund and the BSUoS Working Capital Facility to meet balancing costs in that period, it may set a revised Fixed BSUoS Price for the rest of it.
The revised price covers only the remaining settlement days, NESO must use reasonable endeavours to consult before applying it, and the minimum notice is five business days. A budget built on the published figure should know the possibility is written into the code.
Two settlements, fourteen months apartWhy a BSUoS charge for a period you closed keeps arriving.+
BSUoS settles in stages, and all three are counted from the settlement day rather than from each other. An indicative run follows within about a week and is not billed. Initial settlement, the run suppliers are actually charged on, follows sixteen working days after the settlement day. Final reconciliation lands roughly fourteen months after it, recalculated on final settlement data and with interest as defined in the CUSC.
The rate does not move between those runs, because it is fixed. The volume does, because Elexon reconciles estimated consumption against actual over the same period. So a reconciliation is a volume correction priced at the original tariff, which is the fastest way to tell a legitimate one from a mistake.
Energy intensive manufacturers get most of it backNot through the exemption, through the scheme that travels with it.+
An Energy Intensive Industries certificate exempts a certified proportion of four policy levies and does not touch BSUoS. The Network Charging Compensation Scheme, open to any valid certificate holder without a further test, refunds 90% of eligible BSUoS, DUoS and TNUoS charges on that same certified proportion, at 90% for charges incurred from 1 April 2026 and 60% for those incurred before it. Because the scheme pays twelve months in arrears, the first payment at the higher rate arrives after April 2027, and a claim lodged in 2026 is for earlier charges at the old rate.
The catch is evidential. Compensation is claimed quarterly, on charges actually incurred and paid, in a window that cannot be reopened, and a bundled non-commodity line does not evidence a BSUoS cost. The guide to the scheme covers the claim process in full.
Questions
What is BSUoS on my electricity bill?+
BSUoS stands for Balancing Services Use of System. It is the charge that recovers what the National Energy System Operator spends keeping electricity supply and demand matched in real time, second by second, including paying generators to turn up or down and large users to shift load. It is set by NESO under Section 14 of the Connection and Use of System Code, charged per unit of electricity consumed. Your supplier is the party the code makes liable, not an agent collecting for NESO, which is why a fully fixed contract can price it at whatever the supplier likes.
What is the BSUoS rate for 2026?+
For settlement days from 1 April 2026 to 30 September 2026 the Fixed BSUoS Price is £13.74 per MWh, which is 1.374p per kWh. For 1 October 2026 to 31 March 2027 it is £12.49 per MWh, or 1.249p per kWh. NESO published both as final on 29 December 2025 in its Final BSUoS Tariffs for 2026/27, so they were known nine months before the second one applies.
Why did my BSUoS charge change on 1 October?+
Because the fixed price period changed. BSUoS is set in two six-month tariffs a year, April to September and October to March, and the rate steps at midnight on the boundary. On 1 October 2026 it moves from £13.74 to £12.49 per MWh, a fall of £1.25 per MWh or 9.1%. A billing period that spans the boundary should be split, with each part priced at the tariff for the settlement days it contains.
Is BSUoS the same everywhere in Great Britain?+
Yes. Unlike distribution and transmission charges, BSUoS has no zones, no bands and no regional variation. It is one national price per MWh applying to every settlement day in the fixed price period, so two identical sites at opposite ends of the country pay exactly the same rate per unit. It also does not vary by time of day, which it did before April 2023.
Can I reduce my BSUoS charge?+
Only by consuming less. There is no time band to shift out of and no capacity to reduce, because the rate is flat across every settlement period in the fixed price period. The two exceptions are structural rather than operational: holders of an Energy Intensive Industries certificate can claim network charging compensation on eligible BSUoS, and electricity you generate and consume behind the meter never reaches the charging base at all.
Do generators pay BSUoS?+
Not since 1 April 2023. CUSC modification CMP308, which Ofgem approved on 25 April 2022, moved BSUoS off generation entirely so that it is now recovered from final demand only. Final demand means electricity consumed other than for the purposes of generation or export onto the network. Interconnector BM Units and the BM Units of Virtual Lead Parties are also not liable, under CUSC paragraph 14.31.14.
What is BSUoS in p/kWh?+
Divide the published £/MWh figure by ten. A tariff of £13.74 per MWh is 1.374p per kWh, and £12.49 per MWh is 1.249p per kWh. NESO publishes the tariff in pounds per MWh and most suppliers bill in pence per kWh, which is the single most common source of a factor-of-ten error when somebody checks the line by hand.
Why is my BSUoS line higher than the tariff times my metered kWh?+
Because BSUoS is charged on gross demand volume at the network boundary, not on the units your meter recorded. The difference is the electricity lost as heat in the network between the boundary and your site, applied as a line loss factor that varies by network, voltage and time of day. A hand calculation against metered volume alone will come out a few percent light, and that is expected rather than an error.
Can the BSUoS rate change part way through a fixed period?+
Yes, but only in one narrow case. Under CUSC paragraph 14.31.15, if NESO forecasts that it will neither recover enough through BSUoS charges nor hold enough in the Industry BSUoS Fund and the BSUoS Working Capital Facility to meet balancing costs, it may set a revised Fixed BSUoS Price for the rest of the period. It must use reasonable endeavours to consult first and give a minimum of five business days notice.
Why am I being billed BSUoS for a period I already paid for?+
Because BSUoS settles twice. NESO calculates an initial settlement charge shortly after each settlement day, then a Final Reconciliation charge around fourteen months later using the final settlement data, with interest as defined in the CUSC. Your metered volume for that day will have been revised in the meantime, so a reconciliation line for an old period is normal. Whether the amount is right is a separate question.
Does the EII exemption cover BSUoS?+
Not the exemption, but the compensation scheme that comes with it does. An Energy Intensive Industries certificate removes a certified proportion of four policy levies and never touches BSUoS. The Network Charging Compensation Scheme, which any valid certificate holder can claim under, refunds 90% of eligible BSUoS, DUoS and TNUoS charges on that same certified proportion. The 90% attaches to charges incurred from 1 April 2026, not to claims made from that date, and because the scheme pays twelve months in arrears the first payment at the higher rate arrives after April 2027.
One published rate. Either the line matches it or it does not.
Simplest Energy rebuilds the BSUoS line from the NESO tariff for the settlement days billed, splits the period at a tariff boundary, and compares the result against the invoice.
- BSUoS priced from the published NESO fixed tariffs, with a period split at a tariff boundary and each part priced at its own rate
- Historic periods priced from the published half-hourly rates, joined to actual consumption per settlement period
- Metered volume grossed up by the published line loss factor, where the data covers the meter
- Generation-side BSUoS, out of scope while the charge is recovered from demand only
- The Network Charging Compensation claim value for certified sites, which refunds BSUoS in arrears rather than removing it from the invoice
Built from the primary document.
Balancing Services Use of System (BSUoS) charges
Final BSUoS Tariffs for 2026/27: Fixed Tariff 7 and Fixed Tariff 8
CUSC Section 14, Charging Methodologies
Introduction to Balancing Services Use of System Charges (BSUoS)
CMP308: Removal of BSUoS charges from Generation
CMP361 and CMP362 Decision
Current and historic BSUoS data, by settlement period
- Last reviewed
- 2 September 2026
- Technical basis
- NESO Final BSUoS Tariffs for 2026/27 v1.0 (29 December 2025), CUSC Section 14 v1.48a (1 April 2026) and the NESO BSUoS guidance document (February 2025), all checked 2 September 2026
- Review trigger
- NESO publishing Final Tariffs 9 and 10 for 2027/28, due by 31 December 2026; a revised Fixed BSUoS Price issued mid-period under CUSC paragraph 14.31.15; or an Ofgem decision on CMP453.
This guide explains how BSUoS is set and calculated. It is not tax, legal or procurement advice, and the tariffs quoted are those NESO published as final for the 2026/27 charging year at the date of review. A fixed tariff can be revised mid-period under the CUSC, so check the linked source before relying on a figure.
