Skip to the content

DUoS charges, explained.

What Distribution Use of System charges pay for, who sets them, how the red, amber and green bands work, and a full month of DUoS rebuilt from the published 2026/27 rates for two network areas.

The one-minute version

What are DUoS charges?

Distribution Use of System charges pay for the local electricity network between the grid supply point and your meter. They are set by the distribution network operator for your region, not by your supplier, published a year and a quarter before they apply, and collected by the supplier on behalf of the operator. A half-hourly site pays them as three time-banded unit rates, a daily fixed charge, a charge on its agreed capacity, and a charge on reactive power.

Because the rates differ by region, by voltage and by time of day, DUoS is the part of a business bill that moves most when nothing about your consumption has changed. It is also the part most worth checking, because every figure in it is published by name.

Red band against green band
223x
Southern Electric Power Distribution charges 6.243p per kWh in the red window and 0.028p in the green one, on the same tariff, for 2026/27.
Notice before a rate applies
15 months
DCUSA clause 19.1A requires a network operator to give fifteen months of written notice of the charges that will apply from a given 1 April.
GB distribution network areas
14
Each publishes its own tariffs and its own band windows. Two identical sites in different areas pay materially different amounts.

What DUoS pays for, and who sets it

Electricity reaches a site over two networks. The transmission system carries it across the country at very high voltage and ends at a grid supply point. From there the distribution system carries it the rest of the way, stepping the voltage down as it goes, until it reaches a meter. DUoS is the charge for that second journey.

Great Britain is divided into fourteen distribution network areas, each run by a licensed distribution network operator. The operator owns the wires, the substations and the transformers in its region, and is paid an allowed revenue set by the regulator through the price control. DUoS is how it recovers that revenue from the people who use the network, whoever supplies them.

The instrument

The rates are not a commercial decision. Standard Licence Condition 14 of the electricity distribution licence obliges each operator to publish a use of system charging statement, and the charges in it are calculated under methodologies set out in the Distribution Connection and Use of System Agreement, the industry code that governs connection to and use of the distribution networks.

  • Schedule 16, the CDCM. The Common Distribution Charging Methodology, which sets the charges for low voltage and high voltage designated properties. This is the methodology behind almost every business bill, and the one this guide describes.
  • Schedule 17, the EDCM. The Extra-High Voltage Distribution Charging Methodology, for the Designated EHV Properties the licence assigns to it. The statement puts that threshold at 22kV, which is where it defines Extra-High Voltage as beginning. EDCM charges are calculated site by site rather than from a published tariff table.
  • Schedule 29, the PCDM. The Price Control Disaggregation Model, which sets the discount percentages used for licensed distribution network operators embedded inside another network.

Forward-looking and residual

Every DUoS tariff is built from two different ideas, and telling them apart explains most of what looks strange in a schedule of charges.

The forward-looking part signals to users how their behaviour affects future network costs. It is the reason peak-time units cost more than overnight ones, and the reason capacity is charged for at all. Ofgem is explicit that the revenue recovered from forward-looking elements is typically less than the allowed revenue due to be recovered, because a lot of network cost does not change with use.

The residual part closes that gap. It is the difference between what the forward-looking charges bring in and what the operator is allowed to recover, and since the Targeted Charging Review it is collected through fixed charges rather than through anything a site can avoid by shifting demand. Domestic customers sit in a single band. Non-domestic customers are allocated to one of four residual charging bands for each charge structure, with boundaries calculated nationally under Schedule 32 of the DCUSA. A site certified as non-final demand pays no residual at all and goes onto a No Residual tariff.

Which tariff your meter is on

A schedule of charges runs to dozens of tariffs and only one of them is yours. Four things decide which, in this order, and the operator decides all four rather than your supplier.

  1. 01The network area
    The first two digits of the MPAN are the distributor identifier, and they name the operator whose schedule applies. Southern is 20, north Scotland is 17, London is 12. Nothing else about the supply changes this.
  2. 02The voltage of connection
    Low voltage, low voltage substation, or high voltage. The operator decides it, generally from where the metering sits and where responsibility for the equipment passes from the operator to the customer. Extra-high voltage leaves the CDCM entirely and is charged under the EDCM.
  3. 03How the meter is settled
    A site whose consumption reaches the operator as site-specific half-hourly data is billed the full set of components. A site settled on aggregated data is billed a fixed charge and three unit charges only, with no capacity and no reactive power charge.
  4. 04The residual charging band
    One of four for non-domestic customers, allocated by agreed capacity for site-specific billing and by consumption for aggregated billing. It is the reason the same tariff name appears four times in a schedule with four different sets of numbers.

The result of those four is a Line Loss Factor Class, also called a DUoS Tariff ID: a short code in the operator schedule that names exactly one row of rates. If you can find that code on a bill or from your supplier, you can look your own rates up in the published document and check them line by line. If you cannot, nothing else in this guide is much use, so it is the first thing worth asking for.

The components a DUoS charge is made of

A site-specific DUoS charge is not one number. Under the CDCM it is up to seven separate charges on four different bases, and they can move independently of each other.

Units

Red, amber and green rates in pence per kWh, applied to the units consumed inside each published window.

Fixed

Pence per MPAN per day, for every day of the billing period, whether the site ran or not. This is where the residual sits.

Capacity

Pence per kVA per day on the maximum import capacity on record with the operator, used or not.

Reactive

Pence per kVArh on reactive units above the allowance, which is set by a power factor threshold of 0.95.

The seven CDCM charge components, with the Southern rates for 2026/27
ComponentBasisWhat it is applied toLV Site Specific Band 2
Red unit chargep/kWhUnits consumed inside the red window6.243p
Amber unit chargep/kWhUnits consumed inside the amber window0.509p
Green unit chargep/kWhEverything else, which is most of the week0.028p
Fixed chargep/MPAN/dayEvery day of the billing period0.00p
Capacity chargep/kVA/dayAgreed capacity multiplied by days, used or not10.63p
Exceeded capacity chargep/kVA/dayCapacity taken above the agreed figure, when a breach occurs10.63p
Reactive power chargep/kVArhReactive units above the 0.95 power factor allowance0.251p

Two of those are worth pausing on. The capacity charge is not a charge for electricity: it is rent on a reservation, paid daily against the maximum import capacity agreed with the operator, and it is owed in full by a site that ran at a fraction of it or did not run at all. The reactive power charge is not a charge for electricity either. It applies to the reactive units a site draws above a threshold, and Southern sets that threshold at 33% of active units, which is what a power factor of 0.95 works out to.

Both are among the very few lines on a business bill a site can act on directly. Agreed capacity can be reduced by agreement with the operator, and reactive power charges are described in the Southern statement itself as generally avoidable where the electrical installation is designed to hold a power factor between 0.95 and unity. Both are covered in more detail in the agreed capacity and reactive power glossary entries.

Red, amber and green, and why the windows differ

The three unit rates are the part of DUoS most people have heard of and the part most often described wrongly. The bands are not national. Each operator publishes its own windows in its own schedule, and they differ in start time, in length and in what happens at weekends.

Two rules hold across the operators covered here. All times are UK clock time, which means the windows move with the clocks rather than staying fixed in UTC. And bank holidays count as weekdays, which catches out anyone who assumes a public holiday is charged like a Sunday.

Metered time bands for 2026/27, as published by each operator
BandSouthern (SEPD)North Scotland (SHEPD)
Red, weekdays including bank holidays16:30 to 19:30, all year16:00 to 19:00, all year
Amber, weekdays including bank holidays07:00 to 16:30 and 19:30 to 22:0007:00 to 16:00 and 19:00 to 21:00
Green, weekdays including bank holidays00:00 to 07:00 and 22:00 to 24:0000:00 to 07:00 and 21:00 to 24:00
Amber, Saturday and Sunday09:30 to 21:3012:00 to 20:00
Green, Saturday and Sunday00:00 to 09:30 and 21:30 to 24:0000:00 to 12:00 and 20:00 to 24:00

Three hours a weekday sit in the red band in both areas, which is 66 hours out of the 720 in a thirty day month, or nine per cent of the month. The pricing does not follow that proportion at all. On the Southern LV Site Specific Band 2 tariff the red rate is 6.243p per kWh and the green rate is 0.028p, so a unit moved out of the red window and into the green one costs a two hundred and twenty third of what it did.

That ratio is the single most useful thing to know about distribution charges. It means the share of a DUoS bill that came from red-band consumption is almost never the share of kWh that landed in the red band, and it means load shifting is worth far more against DUoS than the headline unit rate on a supply contract suggests.

A month of DUoS at published rates

Here is a complete DUoS charge for one month, at the rates published for the 2026/27 charging year. The site is an assumption and is labelled as one. Every rate, every band window and the reactive threshold are the published figures.

Assume a half-hourly low voltage site in the Southern area, on the LV Site Specific Band 2 tariff, LLFC H87. Assume it holds 500 kVA of agreed capacity, that it draws a steady 400 kW around the clock through September 2026, and that it runs at a power factor of 0.90. September 2026 has 22 weekdays, 8 weekend days and no bank holiday, and a steady 400 kW over its 720 hours is 288,000 kWh.

Red, 66 hours at 400 kW
26,400 kWh
Amber, 360 hours at 400 kW
144,000 kWh
Green, 294 hours at 400 kW
117,600 kWh
Red at 6.243p per kWh
£1,648.15
Amber at 0.509p per kWh
£732.96
Green at 0.028p per kWh
£32.93
Fixed at 0.00p per MPAN per day, 30 days
£0.00
Capacity at 10.63p per kVA per day, 500 kVA, 30 days
£1,594.50
Reactive at 0.251p per kVArh on 44,438.4 chargeable kVArh
£111.54
DUoS for the month
£4,120.08

Where the reactive figure came from

A power factor of 0.90 means reactive import runs at 0.4843 kVArh for every kWh, so 288,000 kWh comes with 139,478.4 kVArh. The Southern allowance is 0.33 kVArh per kWh, which is 95,040 kVArh over the month, and only the excess is chargeable. 139,478.4 less 95,040 is 44,438.4 kVArh, which at 0.251p is £111.54. Correcting the power factor to 0.95 would remove that line entirely.

That single subtraction works here only because the load and the power factor are assumed constant. Paragraph 2.53 of the statement does the calculation in every half hour and sums the results, so on a real site the good half hours cannot pay for the bad ones. Rebuilding a month from monthly totals nets them off and returns a smaller chargeable figure than a correct invoice, which reads as an overcharge when it is a rebuilding error.

What each component actually contributed

The interesting part is not the total. It is how little the proportions look like the consumption.

Share of units against share of cost, Southern LV Site Specific Band 2, September 2026
ComponentShare of the kWhShare of the DUoS bill
Red units9.2%40.0%
Amber units50.0%17.8%
Green units40.8%0.8%
Capacityno kWh at all38.7%
Reactive powerno kWh at all2.7%

Nine per cent of the units carried forty per cent of the bill. Forty-one per cent of the units carried less than one per cent of it. And more than a third of the charge came from two components that are not measured in kWh at all, so no amount of energy efficiency touches them.

The same site, moved to the north of Scotland

Now take the identical site, the identical month, the identical load and the identical tariff name, and put it in the north Scotland area instead. The band windows are different, so the consumption falls differently, and the rates are different too.

Red, 66 hours at 400 kW
26,400 kWh
Amber, 306 hours at 400 kW
122,400 kWh
Green, 348 hours at 400 kW
139,200 kWh
Red at 8.049p per kWh
£2,124.94
Amber at 2.321p per kWh
£2,840.90
Green at 0.299p per kWh
£416.21
Fixed at 0.00p per MPAN per day, 30 days
£0.00
Capacity at 13.83p per kVA per day, 500 kVA, 30 days
£2,074.50
Reactive at 0.442p per kVArh on 44,438.4 chargeable kVArh
£196.42
DUoS for the month
£7,652.97

Nothing about the business changed. The same 288,000 kWh cost £4,120.08 in distribution charges in one area and £7,652.97 in the other, a difference of £3,532.89 in a single month, because the two operators run different networks with different costs and recover them from different numbers of customers. This is what people mean when they say network charges are regional, and it is why a DUoS rate quoted without a network area attached is not a rate at all.

Where it appears on your invoice

The operator publishes seven component names. Suppliers do not use them. The same component appears on invoices under several different labels, and the same label can mean different components at different suppliers, which is why a bill that shows a distribution total and nothing else is effectively unauditable.

What the operator calls each component, and what an invoice tends to call it
Component in the scheduleLabels seen on invoicesCharged on
Red unit chargeDUoS Red, DUoS Red Unit Rate, Unit Rate 1kWh in the red window
Amber unit chargeDUoS Amber, DUoS Amber Unit Rate, Unit Rate 2kWh in the amber window
Green unit chargeDUoS Green, DUoS Green Unit Rate, Unit Rate 3kWh in the green window
Fixed chargeDUoS Fixed, DUoS Fixed Charge, DUoS Standing Charge, Fixed Charge DistributionDays in the billing period
Capacity chargeAvailability, Availability Charge, Capacity, Capacity ChargeAgreed capacity multiplied by days
Exceeded capacity chargeExceeded Capacity, Excess CapacityCapacity taken above the agreed figure
Reactive power chargeReactive Power, Reactive Power ChargeChargeable kVArh

Unit Rate 1, 2 and 3 are the trap in that table. On a supply contract those three labels usually mean day, night and weekend energy rates. On the distribution section of the same invoice they usually mean red, amber and green. Reading one as the other produces a comparison that looks arithmetically fine and is answering a different question.

How to check it

DUoS is one of the few charges on a business bill that can be reproduced exactly rather than sampled, because the operator publishes every input except your consumption. Working in this order matters, because a failure early on makes everything after it meaningless.

  • The tariff. Take the LLFC or DUoS Tariff ID for the meter and find that row in the operator schedule for the charging year the bill covers. A wrong tariff produces a perfectly arithmetic bill for somebody else.
  • The charging year. Rates change on 1 April. A bill spanning that date needs two sets of rates, one for each side of it, and a single blended rate across the boundary is wrong by construction.
  • The band allocation. Check the kWh billed in each band against half-hourly data allocated to the published windows for that operator, in UK clock time, with bank holidays treated as weekdays.
  • The rates. Compare each component against the published figure to the last decimal place the schedule prints. Distribution rates run to three decimal places of a penny and get truncated to two in transcription more often than they get typed wrongly.
  • Capacity. Multiply the agreed capacity by the days in the period. Then ask a separate question: is the agreed capacity anywhere near the real peak? A capacity set for equipment that left the site years ago is the most common recurring overcharge in this whole area, and it is fixable.
  • Reactive power. Rebuild the allowance before comparing the amount, and rebuild it half hour by half hour rather than from the month, which is how the statement computes it. A reactive line billed on total kVArh rather than on kVArh above the threshold is a large error that looks like a small one.

One thing not to check, because it is not there. Line loss factors gross metered volume up for several charges on a bill, and distribution is not one of them. The Southern statement is explicit that the loss adjustment is used in settlement and does not affect distribution charges. A DUoS line reconstructed from grossed-up volume will be a few per cent too high, and the error will look like a supplier overcharge.

What is changing

Two things are moving in distribution charging, and both of them are visible in the 2026/27 rates rather than being a forecast.

Surplus residuals broke the model, and are being patched

When the residual comes out negative, the CDCM discounts fixed charges and unit rates to bring recovery down to target. A large enough surplus residual exhausts that discounting and the model stops producing a complete set of tariffs. Something has to give, because an operator that cannot publish a tariff for a group of sites cannot bill them at all.

For 2026/27 this was live. Ofgem directed three network operators to depart from the notice period and the charging methodologies. In the Southern and north Scotland areas the intervention was a scaler applied to the gross asset values in the Distribution Reinforcement Model, 99% in Southern and 82% in north Scotland. Without it, Ofgem recorded that high voltage site specific customers in bands 3 and 4 in Southern, roughly 550 meter points, and bands 2, 3 and 4 in north Scotland, roughly 200 meter points, would not have been billable at all.

You can see the result in the published tables. The Southern HV Site Specific Band 4 tariff for 2026/27 carries a red unit charge of 0.000p, an amber charge of 0.000p, a green charge of 0.000p and a fixed charge of 0.00p. Everything that site pays in distribution charges comes from its capacity charge of 10.06p per kVA per day and its reactive power charge of 0.098p per kVArh.

The permanent fix is DCUSA modification DCP450, approved by Ofgem on 20 October 2025, which adds a step to the CDCM letting operators reduce the gross asset value input uniformly so that tariffs can be produced without a derogation. It takes effect on 1 April 2027 and applies to the CDCM only. Nothing equivalent has yet been raised for the EDCM, which is why extra-high voltage sites are still being handled case by case.

Notice periods are being cut, one year at a time

The fifteen months of notice in clause 19.1A is the reason DUoS is checkable so far ahead. It is also the first thing to go when the model misbehaves. Ofgem can direct an operator to depart from it under clause 19.1B, and the notice period then drops to forty days. It did so for SSEN on 19 December 2025 in respect of the 2027/28 charges for both its areas, with publication expected by 31 January 2026 rather than 31 December 2025.

If you budget from published DUoS rates, this is the practical consequence: the fifteen month figure is a default rather than a guarantee, and in an affected area the final tariffs for a charging year may not exist until the January before it starts.

Deep dives and edge cases

The main path above covers the bill most half-hourly sites receive. These come up often enough to answer and not often enough to interrupt it.

  1. 15 months aheadThe charges are published

    DCUSA clause 19.1A requires written notice of the charges that will apply from a given 1 April. Embedded network operators follow one month later, at 14 months.

  2. 1 AprilThe charging year begins

    Every rate in the schedule takes effect at once and runs to 31 March. A bill spanning the date needs both years of rates.

  3. Each periodThe operator bills the supplier

    DUoS is charged to the supplier, not to you. What reaches your invoice depends on whether your contract passes it through or fixes it.

  4. Up to 14 monthsAggregated volumes are reconciled

    Southern states that invoices on the aggregated approach are reconciled over roughly 14 months as more accurate consumption arrives, dropping to 4 months once half-hourly settlement is in place.

Exceeded capacity, and how long a breach costs youOne half hour over the agreed capacity is not charged for one half hour.

Where a site draws more than its agreed capacity, the excess is charged at the exceeded capacity rate, which for the Southern LV Site Specific tariffs is the same 10.63p per kVA per day as the capacity charge itself. The excess is worked out for every half hour from active import and reactive flows, and the largest value in the period is the one applied.

The part that costs money is the duration. Southern charges the exceeded capacity for the duration of the full month in which the breach occurs, not for the half hour or the day it happened on. A single half hour of overrun in a thirty day month is charged as thirty days of the excess.

That also means the arithmetic is worth doing before asking for a capacity reduction. Reductions are permitted once in any twelve month period, cannot be made within twelve months of agreeing the capacity, and take effect from the start of the next billing period after the request. Cutting agreed capacity too far and then breaching it repeatedly costs more than leaving it alone.

Why a No Residual tariff can be dearer than a banded oneThe counter-intuitive shape of a 2026/27 schedule, and what causes it.

A No Residual tariff exists for sites certified as non-final demand, which pay no residual element. Intuitively that should be the cheapest tariff in the table. In the Southern schedule for 2026/27 it is the dearest: LV Site Specific No Residual charges 8.530p in the red band against 6.243p on Band 2, and carries a 28.20p daily fixed charge where the banded tariffs carry none.

The reason is that the residual for those bands is a surplus rather than a cost, so paying it is worth something and being excused it is not. The banded tariffs receive a discount that the No Residual tariff does not. It is a real feature of this charging year rather than an error, and it is exactly the kind of thing that makes a rate sanity check based on intuition unreliable.

Aggregated sites see a different billSmaller sites, fewer components, and what half-hourly settlement changes.

A site whose consumption reaches the operator as aggregated rather than site-specific data is billed a fixed charge and three unit charges, and nothing else. No capacity charge, no exceeded capacity charge, no reactive power charge. That is not a concession, it is a consequence of the operator not having the data those components need.

The residual band for such a site is allocated by consumption rather than by agreed capacity, and the same is true for sites under the transitional protection arrangements for half-hourly settlement migration. As settlement moves onto actual half-hourly data for every meter point, the boundary between the two billing approaches moves with it.

Generation, and charges that run backwardsExport can attract a credit rather than a charge.

Where a generation connection supports the distribution system, the charges are negative and the supplier receives credits for exported energy. In the Southern schedule for 2026/27 the LV Generation Site Specific tariff carries unit charges of minus 8.447p, minus 1.124p and minus 0.057p per kWh across the three bands, with a reactive power charge of 0.313p per kVArh that remains positive.

Two consequences follow. Export credits are largest in the red window, which is the mirror image of the demand signal and the reason a battery or a generator is worth dispatching into the early evening. And a site with both import and export has two sets of charges running in opposite directions, which is a common source of confusion when a bill is read as a single number.

Embedded networks and out of area suppliesWhen the network your meter sits on is not the one the postcode suggests.

A site connected inside a private or independently owned network is served by a licensed distribution network operator embedded in the host network. The host still charges the embedded operator for use of its system, at a discount set under Schedule 29 of the DCUSA, and the embedded operator publishes its own charges on top.

Practically this means two things. The rates in the host operator schedule are not your rates, so checking against them will not reconcile. And the discount structure is published in the same statement, in the LDNO annex, so the arithmetic is still reproducible once you know which network you are actually on.

What a fixed contract does to all of thisFixed does not mean the charge is not there.

On a fully fixed contract the distribution charges are wrapped into the unit rate at a level agreed up front, and the supplier carries the risk that they rise. That risk is priced, so a fixed contract has pre-paid an estimate of DUoS plus a premium rather than avoided it.

On a pass-through contract the charges appear as their own lines and move with the schedule. This is the case where checking pays, and it is also the case where load shifting and a capacity review turn into cash rather than into a better outcome for the supplier. Which of the two you have is a term of the contract, and it is worth reading rather than assuming. The guide to a business electricity bill covers the difference across every line rather than just this one.

Getting DUoS compensated rather than reducedEnergy intensive manufacturers can claim a share of it back.

DUoS is one of the three network charges covered by the Network Charging Compensation Scheme, alongside transmission and balancing charges. A manufacturer holding a valid Energy Intensive Industries certificate can claim a share of eligible distribution charges back on the certified proportion of each meter.

The catch is evidential rather than technical: a claim needs the distribution charges shown on the bill, which a combined non-commodity line does not do. The EII exemption guide covers the certificate, the claim windows and what counts as evidence.

Questions

What are DUoS charges on my electricity bill?

DUoS stands for Distribution Use of System. It is the charge for using the local electricity network that carries power from the grid supply point to your meter. It is set by the distribution network operator for your region under the Common Distribution Charging Methodology in Schedule 16 of the Distribution Connection and Use of System Agreement, published in an annual charging statement, and collected by your supplier on the operator's behalf. Your supplier does not set it and cannot negotiate it.

Why has my DUoS charge gone up when my usage has not?

There are four common reasons. Rates reset on 1 April for every network area at once, so a bill either side of that date is charged at different numbers. The billing period may be longer, because the fixed and capacity charges are per day rather than per unit. The shape of demand may have moved, because a unit consumed in the red window can cost hundreds of times what the same unit costs overnight. Or the site may have been reallocated to a different residual charging band or a different tariff, which the network operator decides rather than your supplier.

What are the DUoS red, amber and green bands?

They are three time windows, published by each distribution network operator for its own area, that decide which of three unit rates applies to each unit consumed. Red covers the weekday evening peak and is by far the dearest. Amber covers the rest of the working day. Green covers nights and most of the weekend and is the cheapest. The windows are published in Annex 1 of the operator's charging statement, are stated in UK clock time, and are not the same in any two network areas.

What time is the DUoS red band?

It depends on the network area. For 2026/27 Southern Electric Power Distribution sets it at 16:30 to 19:30 on weekdays including bank holidays, all year round. Scottish Hydro Electric Power Distribution sets it at 16:00 to 19:00 on the same days. There is no national red band time, so a red band quoted without a network area attached is not usable. Check Annex 1 of the charging statement for the operator identified by the first two digits of your MPAN.

How much more is the red rate than the green rate?

On the Southern LV Site Specific Band 2 tariff for 2026/27 the red unit charge is 6.243p per kWh and the green unit charge is 0.028p per kWh, so a unit consumed in the red window costs about 223 times what the same unit costs in the green window. That ratio is why the share of a DUoS bill that came from red band consumption is almost never the share of kWh that landed there.

Do DUoS bands treat bank holidays as weekdays or weekends?

As weekdays. Both the Southern and the north Scotland charging statements for 2026/27 define the weekday bands as Monday to Friday including bank holidays, so a site that shuts on a public holiday is still exposed to red band pricing that day if it draws load in the evening peak. Any check of banded volumes that treats bank holidays as weekends will disagree with the invoice.

What is a DUoS availability or capacity charge?

It is a daily charge in pence per kVA on the maximum import capacity agreed with your distribution network operator, and it is owed whether or not the capacity is used. On the Southern LV Site Specific tariffs for 2026/27 it is 10.63p per kVA per day. It appears on invoices as availability, availability charge, capacity or capacity charge. Capacity set well above the real peak of the site is the most common recurring overcharge in distribution charges, and the operator can reduce an agreed capacity on request.

What is the DUoS reactive power charge and can I avoid it?

It is a charge in pence per kVArh on the reactive units a half-hourly site draws above an allowance set by a power factor threshold of 0.95, which works out at 33 per cent of active units. On the Southern LV Site Specific tariffs for 2026/27 it is 0.251p per kVArh. It is one of the few bill lines that can be eliminated rather than reduced: correcting power factor to between 0.95 and unity removes the chargeable volume, and the Southern statement describes the charge as generally avoidable where the installation is designed for it.

Should line loss factors be applied to DUoS?

No. Line loss factors gross metered volume up for settlement and for several other charges on a bill, but not for distribution charges. The Southern charging statement states plainly that the loss adjustment is used in settlement and does not affect distribution charges. A DUoS line rebuilt from grossed-up volume will come out a few per cent too high, and the error will look like a supplier overcharge.

What is an LLFC or DUoS Tariff ID?

It is the short code that names exactly one row of rates in your network operator's schedule of charges. The operator assigns it from the network area, the voltage of connection, how the meter is settled and the residual charging band the site falls into. Without it you cannot look your own rates up, so it is the first thing to ask a supplier for. Examples for 2026/27 are H87 for Southern LV Site Specific Band 2 and P82 for the same tariff in north Scotland.

How far in advance are DUoS charges published?

Clause 19.1A of the Distribution Connection and Use of System Agreement requires a distribution network operator to give fifteen months of written notice of the charges applying from a given 1 April, and embedded network operators fourteen months. Ofgem can direct an operator to depart from that under clause 19.1B, in which case the notice period drops to forty days. It did so for both SSEN areas on 19 December 2025 in respect of the 2027/28 charges, so the fifteen month figure is a default rather than a guarantee.

Why is a No Residual tariff more expensive than a banded one?

Because in 2026/27 the residual for several tariffs came out negative, a case Ofgem calls a surplus residual. Where that happens the Common Distribution Charging Methodology discounts fixed charges and unit rates to bring revenue recovery back down to target, so a site that pays the residual receives the discount and a site excused it does not. In the Southern schedule the LV Site Specific No Residual tariff charges 8.530p in the red band against 6.243p on Band 2, and carries a 28.20p daily fixed charge where the banded tariffs carry none.

Explanation, meet evidence.

Distribution charges, rebuilt component by component.

Simplest Energy reconstructs each DUoS component from the published Schedule of Charges for your network area and charging year, then compares it against what you were billed.

Available now
  • Published Schedules of Charges held for all fourteen GB distribution network areas, byte-exact as published
  • Red, amber and green windows applied per operator and charging year, with half-hourly consumption allocated to them
  • Each component compared separately, so a wrong capacity charge is not hidden by a right unit rate
In development
  • Extra-high voltage site-specific tariffs under the EDCM, which are calculated per site rather than published as a tariff table and are not held today
  • Pricing exceeded capacity on the monthly-breach basis the operators charge on, which today is priced on the days a breach was measured

Built from the primary document.

Primary sourceSouthern Electric Power Distribution plc, version 1.1, 19 February 2026

Use of System Charging Statement, notice of charges effective 1 April 2026

Primary sourceScottish Hydro Electric Power Distribution plc, version 1.1, 19 February 2026

Use of System Charging Statement, notice of charges effective 1 April 2026

Primary sourceOfgem, November 2024

Guidance for managing the effects of surplus residual charges

Primary sourceOfgem, 6 February 2025

Direction issued to SHEPD and SEPD to derogate from the EDCM and the CDCM

Primary sourceOfgem, 19 December 2025

Direction issued to SSEN to derogate from the DUoS charge setting notice period for 2027/28

Primary sourceOfgem, decision of 20 October 2025

DCP450: Distribution Connection and Use of System Agreement (DCUSA) changes

Primary sourceDistribution Connection and Use of System Agreement

The DCUSA document, including Schedule 16 (CDCM) and Schedule 17 (EDCM)

Last reviewed
2 September 2026
Technical basis
Southern Electric Power Distribution and Scottish Hydro Electric Power Distribution Use of System Charging Statements v1.1, effective 1 April 2026, with the Ofgem surplus residual guidance of November 2024 and the DUoS derogation directions of 6 February 2025 and 19 December 2025, all checked 2 September 2026
Review trigger
The 2027/28 Schedules of Charges published by each network operator, DCUSA modification DCP450 taking effect on 1 April 2027, or a further Ofgem direction to derogate from the CDCM, the EDCM or the fifteen month notice period.

This guide explains how distribution charges are set and calculated. It is not procurement, legal or tax advice, and every rate quoted is the figure published for the 2026/27 charging year in the network area named beside it, checked against the source document on the date of review. Rates differ by network area, by tariff and by charging year, so check the schedule for your own area before relying on a figure.