What are TNUoS charges?
TNUoS, Transmission Network Use of System, is what a site pays for the high voltage network that moves electricity across Great Britain. It is set by the National Energy System Operator under section 14 of the Connection and Use of System Code, published by 31 January each year and applied from the following 1 April. Your supplier collects it. Nobody negotiates it.
Since April 2023 it has been two charges under one name. A fixed residual, a flat daily charge per site set by a band that follows the voltage and the size of the connection, which is now almost all of the money. And a locational charge, which varies by where in the country the site sits, and on a half-hourly meter is settled on demand in three half hours that nobody can know in advance.
- Half hours that set the locational charge
- 3
- The triad: the three settlement periods of highest net system demand between November and February, at least ten clear days apart, confirmed at the end of March.
- Recovered through the residual
- £6.27bn
- The banded daily site charge for 2026/27, up from £3.84bn in 2025/26. It is the great majority of what transmission takes from demand.
- Zones charged nothing per kW
- 7
- Zones 1 to 7, Northern Scotland down to the East Midlands, sit on the zero floor for 2026/27. Zone 14, South Western, pays £14.130209 per kW.
What TNUoS pays for
The transmission system is the high voltage network of pylons, cables and substations that carries power from where it is generated to the point where a regional distribution network takes it on. Transmission Network Use of System charges, in the words of the tariff report itself, recover the cost of installing and maintaining that system in England, Wales, Scotland and offshore.
For 2026/27 the total to be recovered is £7.61 billion. Generators pay £1.23 billion of it on their transmission entry capacity, and demand pays the rest: £6.38 billion, spread across every metered site in Great Britain. That is the number behind every transmission line on every business invoice in the country.
The instrument, and why the rates are knowable in advance
TNUoS is not a price. It is a published methodology with an obligation attached to it. Condition E10 of the Electricity System Operator licence and the Connection and Use of System Code require NESO to publish final tariffs for a charging year. NESO cites paragraph 14.29 for that obligation; the deadline itself is at paragraph 14.14.12, and the methodology that produced the tariffs is the statement of the use of system charging methodology in section 14 of the same code.
In practice that means one fixed point and a rhythm around it. The fixed point is the final tariffs, which paragraph 14.14.12 requires by the end of the preceding January, for effect from 1 April. The draft comes a month or two before that, and the month moves: December for 2026/27, but NESO has scheduled the 2027/28 draft for 30 November 2026. So a transmission charge on an invoice is checkable against a document that existed before the period began.
One caution about that. The same paragraph says NESO may update the tariffs part way through a financial year, and paragraph 14.17.7 sets out how to price it when that happens, by pro-rating the applicable tariffs across the months each one covers. NESO has not exercised the power in recent years, so two rates inside one charging year is unusual. It is not, on its own, a supplier error.
How it differs from the distribution charge beside it
Distribution charges pay for the local network, are set by the operator of the network area a site sits in, and are published in that operator schedule of charges. Transmission charges pay for the national network above it, are set once for the whole country by NESO, and vary by zone rather than by network area. The boundary between the two is the grid supply point, the substation where transmission hands electricity over to distribution.
Three charges under one name
A demand site can face three separate transmission elements, and a fourth exists as a credit rather than a charge. Which of them applies turns on one thing: whether the meter is settled half-hourly, which is the thing Market-wide Half Hourly Settlement is changing for every meter in the country.
| Element | Who pays it | What it is charged on | 2026/27 range |
|---|---|---|---|
| Demand residual | Every final demand site, half-hourly or not | A flat rate per site per day, set by the band the site is allocated to | £0.222566 a day for a domestic site to £5,698.386405 a day for EHV band 4, and £20,829.236682 for the top transmission-connected band |
| Half-hourly locational | Half-hourly settled sites | Average metered demand across the three triad half hours, times the zonal rate per kW | £0 per kW in zones 1 to 7, £14.130209 per kW in zone 14 |
| Non-half-hourly locational | Sites still settled non-half-hourly, and half-hourly sites in measurement classes F and G | Energy consumed between 16:00 and 19:00 every day of the year, times the zonal rate per kWh | 0p per kWh in zones 1 to 7, 2.071095p per kWh in zone 14 |
| Embedded export credit | Sites exporting at a triad from generation under 100 MW | Average metered export across the triad, times the zonal export tariff | An average of £3.045116 per kW, paid out rather than charged |
The proportions are the part people get wrong. Of the £6.38 billion to be recovered from demand in 2026/27, £6.265 billion comes through the residual. The locational element, the one that triad avoidance exists to reduce, is what is left.
One detail worth holding on to: the non-half-hourly window, settlement periods 33 to 38, is the same six half hours the Capacity Market Supplier Charge uses, although that charge takes only the working days between November and February while this one takes every day of the year.
The formula, once
The average of the metered demand in kW across the three triad half hours. On a non-half-hourly supply this term is replaced by energy consumed 16:00 to 19:00 across the year, priced per kWh.
The published rate per kW for the demand zone the site sits in, floored at zero. Seven of the fourteen zones are at that floor for 2026/27.
The published rate per site per day for the band the site is allocated to. Non-locational, so every site in a band pays the same wherever it is.
Every day the site was served, whether or not it consumed anything. The locational term is annual, so a monthly invoice carries its day-count share of it.
How it reaches your bill
NESO does not invoice sites. It invoices suppliers, against the balancing mechanism unit each supplier registers, and the code sets out exactly what that invoice contains: energy, demand locational, transmission demand residual and embedded export, summed.
For the residual the calculation is arithmetic on a site count. NESO multiplies the number of sites a supplier serves in each band, by the number of days it served them, by the rate per site per day for that band. Where one connection site is served by more than one supplier, the charge is divided between them annually in proportion to the consumption each took the previous year.
The locational element cannot be calculated at the time it is billed, because the triad has not happened yet, and when it has happened the metered volumes are not final. So suppliers are billed monthly against forecast volumes and reconciled afterwards, twice, the last of them once Elexon final settlement data is available up to sixteen months after the financial year concerned.
Two consequences reach your invoice. On a fully fixed contract none of this is visible, because the supplier has priced its own estimate of these charges into the unit rate and carries the risk of being wrong. On a pass-through contract all of it is visible, including reconciliations for periods you have already paid for, which is normal and can be large. Which of the two you are on is a term of the contract, and it is covered in the guide to the bill as a whole.
The fixed residual, and your band
Until 2023 the transmission residual, the part of the charge that recovers the fixed cost of the network that already exists, was recovered on triad demand. A site that cut its demand in those three half hours cut its share of the fixed costs with it, and the costs did not go away: they moved onto everyone else.
Ofgem published the Targeted Charging Review decision on 21 November 2019, updated 18 December 2019, and decided that residual charges would be levied as fixed charges on final demand only. Transmission moved onto banded fixed charges from April 2023. The behaviour it was designed to stop, avoiding a fixed cost by moving demand rather than reducing it, is exactly what a fixed daily charge cannot be avoided by.
How the bands are drawn
The code sets one charging band for domestic sites, four for each non-domestic residual charging group connected to a distribution network, four for sites connected directly to the transmission system, and one for unmetered supplies. The four are cut at the 40th, 70th and 85th percentiles of the population in that group, or at the 40th, 70th and 93rd for transmission-connected sites. Twenty two bands are published in total for 2026/27.
Which group a site belongs to follows the voltage of the connection. Within a group, the band follows agreed capacity where the site has one, and annual consumption where it does not. That second case is the whole-current low voltage site with no maximum import capacity on record, which is most small commercial premises.
| Band | What puts a site in it | £ per site per day | £ over 365 days |
|---|---|---|---|
| Domestic | A domestic site, at any voltage | 0.222566 | 81.24 |
| LVN1 | Low voltage, no agreed capacity, up to 3,986 kWh a year | 0.239315 | 87.35 |
| LVN2 | Above 3,986 and up to 13,677 kWh a year | 0.587299 | 214.36 |
| LVN3 | Above 13,677 and up to 27,543 kWh a year | 1.242416 | 453.48 |
| LVN4 | Above 27,543 kWh a year | 3.461015 | 1,263.27 |
| LV1 | Low voltage with agreed capacity up to 90 kVA | 5.797398 | 2,116.05 |
| LV2 | Above 90 and up to 150 kVA | 11.511840 | 4,201.82 |
| LV3 | Above 150 and up to 250 kVA | 14.381374 | 5,249.20 |
| LV4 | Above 250 kVA | 38.180103 | 13,935.74 |
| HV1 | High voltage with agreed capacity up to 500 kVA | 31.839048 | 11,621.25 |
| HV2 | Above 500 and up to 1,100 kVA | 117.152788 | 42,760.77 |
| HV3 | Above 1,100 and up to 2,000 kVA | 185.418505 | 67,677.75 |
| HV4 | Above 2,000 kVA | 528.912335 | 193,053.00 |
| EHV1 | Extra high voltage with agreed capacity up to 3,500 kVA | 325.476550 | 118,798.94 |
| EHV2 | Above 3,500 and up to 11,000 kVA | 1,159.381475 | 423,174.24 |
| EHV3 | Above 11,000 and up to 20,000 kVA | 2,512.930533 | 917,219.64 |
| EHV4 | Above 20,000 kVA | 5,698.386405 | 2,079,911.04 |
The right hand column is the rate multiplied by the 365 days of the 2026/27 charging year, which is what the site actually pays if it is connected for all of it. Nothing in that column depends on consumption, on load shape, on the time of day, or on the region. A 1,500 kVA high voltage site in Inverness and a 1,500 kVA high voltage site in Plymouth pay the same £185.418505 a day.
Who assigns the band, and how long it lasts
For a site connected to a distribution network, the network operator assigns the band, under a methodology it is required to maintain in the Distribution Connection and Use of System Agreement. For a site connected directly to transmission, NESO assigns it, using the mean of the latest 24 months of consumption data where that exists and a defined fallback where it does not.
The assignment then holds for the duration of the transmission owner price control period, not for a year. That is the single most surprising thing about this charge for anyone used to reviewing capacity annually: reducing an agreed capacity does not move the band at the next 1 April. It moves at the next re-banding, or through the intervention process covered in the deep dives below.
Triads, and the locational charge
The locational element is the part of TNUoS that says where a site is. It reflects the cost of moving power to that part of the country, so it rises the further a site sits from where generation is concentrated, which in Great Britain means it rises heading south.
On a half-hourly metered supply it is charged on the triad. The code defines that as the settlement period of highest net system demand in the financial year, plus the two next highest, each separated from the peak and from each other by at least ten clear days, between November and February inclusive. Exports on large interconnectors are excluded from the demand figure.
Three properties follow from that definition and all three matter. The triad is national, not local, so it is the same three half hours for every site in the country. It is determined after the event, from settlement data, so nobody knows on the day whether a given evening was one. And it is confirmed at the end of March, after the charging year it applies to has finished.
| Date | Settlement period | Half hour | Net system demand, MW |
|---|---|---|---|
| Thursday 20 November 2025 | 34 | 16:30 to 17:00 | 40,976 |
| Monday 5 January 2026 | 35 | 17:00 to 17:30 | 45,004 |
| Tuesday 3 February 2026 | 37 | 18:00 to 18:30 | 41,227 |
Note the gaps. Forty six days between the first and the second, twenty nine between the second and the third: the ten clear day rule forces the three peaks apart, which is why they never land in the same cold snap. Note also that two of the three are not the obvious candidates. A site that shed load only on the coldest evenings of the winter would have missed the November one entirely.
The zonal tariffs for 2026/27
There are fourteen demand zones. A site belongs to the zone of the grid supply point group it sits in, which is determined by the distributor identifier at the front of its meter point number, not by anything the site or the supplier chooses.
| Zone | Name | Half-hourly, £ per kW | Non-half-hourly, p per kWh |
|---|---|---|---|
| 1 | Northern Scotland | 0 | 0 |
| 2 | Southern Scotland | 0 | 0 |
| 3 | Northern | 0 | 0 |
| 4 | North West | 0 | 0 |
| 5 | Yorkshire | 0 | 0 |
| 6 | N Wales & Mersey | 0 | 0 |
| 7 | East Midlands | 0 | 0 |
| 8 | Midlands | 2.633945 | 0.358668 |
| 9 | Eastern | 0.063093 | 0.009140 |
| 10 | South Wales | 5.969709 | 0.739032 |
| 11 | South East | 4.368073 | 0.633420 |
| 12 | London | 6.453239 | 0.700677 |
| 13 | Southern | 7.354150 | 1.008120 |
| 14 | South Western | 14.130209 | 2.071095 |
Seven zones are at zero. That is not an absence of data: demand tariffs are floored at zero so they cannot become a payment, and the calculated value for the north of the country is below the floor. For a half-hourly site in Newcastle, Leeds or Glasgow, the entire locational element of TNUoS for 2026/27 is nil, and every pound of transmission on the invoice is residual.
At the other end, zone 14 is charged £14.130209 per kW of triad average demand. A site with 1 MW of demand across the three triad half hours pays £14,130.21 a year in South Western and nothing at all in Northern Scotland, for identical consumption.
A worked example
One site, one month, both elements, at the published 2026/27 rates. The rates are real. The site is not: its size and demand are stated assumptions, and they are the only assumed numbers here.
- Assumed site
- London, zone 12
- Assumed connection
- High voltage, 1,500 kVA agreed capacity
- Residual band, from voltage and capacity
- HV3
- Assumed triad average demand
- 1,100 kW
- Billed period
- 1 to 31 July 2026, 31 days
- Residual: £185.418505 x 31 days
- £5,747.97
- Locational, annual: 1,100 kW x £6.453239
- £7,098.56
- Locational, this period: £7,098.5629 x 31 / 365
- £602.89
- TNUoS for the month
- £6,350.86
Three details in that arithmetic are worth stating because they are where hand calculations go wrong. The residual is charged on days, so a 31 day invoice carries more of it than a 28 day one on identical consumption. The locational charge is annual by construction, so a sub-period takes its day-count share of the year rather than being computed from the days in it. And the total is the sum of two lines each already rounded to the penny, which is how an invoice is built: add the unrounded figures instead and you land a penny higher, at £6,350.87, without either of you being wrong.
The same site over a full year
- Residual, 365 days at £185.418505
- £67,677.75
- Locational, 1,100 kW at £6.453239 per kW
- £7,098.56
- Total TNUoS, 2026/27
- £74,776.31
- Share of it that is residual
- 90.5%
Nine tenths of the transmission bill for this site cannot be moved by anything the site does with its load. It is a function of the meter existing, at that voltage, with that agreed capacity. Moving the site to Northern Scotland would remove £7,098.56 and leave £67,677.75 untouched.
Why it went up
The same site, on the same assumptions, priced at the final 2025/26 tariffs. It sat in band HV3 in both years: the band covered 1,000 to 1,800 kVA in 2025/26 and 1,100 to 2,000 kVA in 2026/27, and 1,500 kVA is inside both.
- Residual 2025/26, 365 days at £121.795409
- £44,455.32
- Locational 2025/26, 1,100 kW at £7.405345 per kW
- £8,145.88
- Total TNUoS, 2025/26
- £52,601.20
- Total TNUoS, 2026/27
- £74,776.31
- Increase
- £22,175.11, or 42.2%
The locational element fell. London went from £7.405345 to £6.453239 per kW. The whole of the increase, and more, is the residual, and the reason is visible in one figure: the revenue NESO recovers through the demand residual rose from £3,836.05 million in 2025/26 to £6,265.17 million in 2026/27. That is the answer to why a transmission charge rose on unchanged consumption. It is also why cutting demand at the triad did nothing about it.
Where it appears on your invoice
There is no standard line name. These are the forms we see, and what each one is likely to contain. The unit beside the figure is more reliable than the wording.
| What the line says | What it usually is | The unit to expect |
|---|---|---|
| TNUoS, Transmission Network Use of System | Both elements combined, or on a low voltage site the residual alone | Often no unit at all, which is why it has to be rebuilt rather than read |
| Transmission charge, Transmission charges | The same thing under a plainer name | Days, or kW, depending on which element it is |
| TNUoS residual, TNUoS fixed, Transmission demand residual, TDR | The banded daily site charge only | A quantity in days, at a rate per site per day |
| TNUoS locational, Triad charge, Transmission locational | The zonal element only | A quantity in kW at a rate per kW, or kWh at a rate per kWh on a non-half-hourly site |
| Non-commodity charges, third party costs, pass-through charges | TNUoS bundled with distribution, balancing and the levies | One figure, which can only be checked in total |
A combined line is legal and common, and it usually carries the distribution charge and the balancing charge alongside transmission. It also means an overcharge on the residual can sit underneath an undercharge on the locational element and the sum will look right. You can ask a supplier in writing for the breakdown, and for a business claiming network charge compensation under the energy intensive industries scheme obtaining that detail is explicitly the responsibility of the applicant.
How to check it
TNUoS is one of the more checkable lines on a business invoice, because both of its rates are published before the year begins and neither of them is negotiated. The errors concentrate in the inputs rather than in the rates.
- The zone. It comes from the distributor identifier at the front of the meter point number, through the grid supply point group, to one of fourteen zones. A site priced in the wrong zone is wrong by the whole locational element, and in seven zones the correct answer is nil.
- The band. Voltage plus agreed capacity, or annual consumption where there is no agreed capacity. One band step at high voltage is the difference between £42,760.77 and £67,677.75 a year.
- The days. The residual is a daily charge, so it should track the length of the billed period exactly and ignore consumption completely. A residual that moves with volume is not a residual.
- The charging year boundary. A period crossing 1 April carries two rates, and the split is by day. A single rate across the boundary is an error in one direction or the other.
- The triad element. Check the dates billed against the published triads for that charging year. A triad charge for a year whose triads have not been published yet is an estimate, whatever the invoice calls it.
- Reconciliations. A large transmission adjustment for an old period is normal. It has to be checked against the final tariff for the year it belongs to, not the year the invoice was issued in.
What is changing
Three things moved on 1 April 2026, and one larger change is still ahead.
The residual pot grew by nearly two thirds
Revenue recovered through the transmission demand residual rose from £3,836.05 million for 2025/26 to £6,265.17 million for 2026/27. Since the residual is a fixed daily charge, that increase reached every site in the country whatever it consumed and whenever it consumed it.
The bands were redrawn
Band thresholds are reviewed and reset at the start of each onshore transmission owner price control period, and 1 April 2026 was the start of one. The thresholds moved with it: high voltage band 3 covered 1,000 to 1,800 kVA in 2025/26 and covers 1,100 to 2,000 kVA now. NESO has stated that these thresholds will hold for the duration of the price control period, so a site that changed band this April has changed band for several years.
One code modification took effect
CMP463, stabilising the specific onshore expansion factors, was approved for implementation on 1 April 2026 and holds those factors at 2025/26 levels. It is the only concluded modification affecting the 2026/27 tariffs, and NESO gives it as part of the reason the zonal tariffs for zones 8 to 14 moved unevenly between its own draft and final publications for the year, alongside changes in nodal demand and embedded generation forecasts.
A larger review is coming
NESO writes in the same report that TNUoS charging is undergoing transition and that there will be substantial changes to charging mechanisms over the next few years, either through the Ofgem charging review or through code modifications. Nothing in that has landed yet. Three publications are scheduled before the tariffs change again: the five-year view of 2027/28 to 2031/32 by 30 September 2026, the draft 2027/28 tariffs by 30 November 2026, and the final 2027/28 tariffs by 31 January 2027.
Deep dives and edge cases
The main path above covers the site most businesses operate. These come up often enough to answer and not often enough to interrupt it.
Challenging your residual bandThe route exists, and it is narrower than most people expect.+
A band assignment holds for the whole price control period, so an appeal is the only way to move it in between. For a site on a distribution network the operator maintains a published methodology for exceptional circumstances resulting in reallocation to a different band within a price control period, and that is where a challenge goes first.
For a site connected directly to the transmission system the bar is written into the code. A material change in circumstances means the voltage of the connection changing with a signed construction agreement, or twelve months of actual metered consumption showing gross consumption more than 50% below or above the figure the band was set from, or a notice to disconnect. A reduction has to be accompanied by a signed letter from a director explaining it.
Where a challenge succeeds, the difference is collected or refunded through the normal reconciliation process rather than as a credit note, and none of this removes the right to refer the matter to Ofgem for determination.
Transmission-connected and unmetered sitesTwo more band families, on a different basis again.+
A site connected directly to the transmission system is banded on annual consumption in MWh rather than on capacity, in four bands cut at the 40th, 70th and 93rd percentiles. For 2026/27 they run from £1,401.949529 per site per day up to 25,131 MWh a year, to £20,829.236682 per site per day above 163,880 MWh. There are 72 such sites in the 2026/27 forecast.
Unmetered supplies, street lighting and similar, are the one band charged on volume rather than per site. The 2026/27 rate is 2.568147p per kWh.
Does triad avoidance still pay?Sometimes, for a smaller prize, and in seven zones not at all.+
Before 2023 reducing demand at a triad reduced both the locational charge and the residual, which is what made it worth building a business process around. Since the residual became a fixed daily charge, only the locational element responds.
What that is worth now depends entirely on the zone. In zones 1 to 7 the tariff is zero for 2026/27, so reducing triad demand saves nothing at all. In zone 14 it is £14.130209 per kW, so a megawatt of avoided triad demand is worth £14,130.21 for the year. The same megawatt avoided in the Eastern zone is worth £63.09.
And there is a second cost to weigh. Triads are not known in advance, so avoidance means responding to forecast peaks several times each winter, most of which turn out not to have been triads. That is a real operational cost against a prize that is now, for many sites, small or zero.
Sites that export at a triadAn embedded export tariff, paid rather than charged.+
A site exporting to the distribution network from generation under 100 MW is paid for the volume it exported across the three triad half hours, at a zonal embedded export tariff averaging £3.045116 per kW for 2026/27. The tariff is floored at zero so it cannot become a charge, and £20.44 million is forecast to be paid out through it in 2026/27.
Two things about it surprise people. Gross demand and export are charged and credited separately rather than netted off against each other. And where the generator is settled in the supplier hub rather than registered centrally, the payment goes to the registered supplier rather than to the generator, so whether it reaches the site is a matter for the supply contract.
Energy intensive manufacturers, and 90% of it backNetwork charge compensation covers TNUoS, on the certified proportion.+
A manufacturer holding a valid Energy Intensive Industries certificate can claim compensation for eligible network charges, and transmission charges are in scope alongside distribution and balancing. Since 1 April 2026 the rate is 90% of the eligible charge on the proportion shown on the certificate, up from 60%.
On the worked example above that would turn £74,776.31 of transmission into roughly £7,478 at a fully certified meter, which is the largest single lever available on this charge to anyone who qualifies. Eligibility, the claim windows and the evidence a claim needs are set out in the EII exemption guide. Sites in Scotland and the north of England should read the exclusions there carefully: the scheme does not compensate a charge that was not incurred.
Changing supplier part way through a yearThe residual follows the days, and the split is done centrally.+
Because the residual is charged per site per day to whichever supplier served the site on that day, a switch does not create a gap or a double charge at the transmission level. Where one connection site is served by more than one supplier, NESO divides the charge between them annually, in proportion to the consumption each took in the previous year.
What can go wrong is downstream of that. A new supplier setting the site up with the wrong voltage or the wrong agreed capacity will pass through the wrong band, and the band it has assumed is not usually printed on the invoice. That is worth checking on the first bill after a switch rather than the twelfth.
Questions
What are TNUoS charges?+
TNUoS, Transmission Network Use of System, is the charge for using the high-voltage network that moves electricity across Great Britain. It is set by the National Energy System Operator under section 14 of the Connection and Use of System Code, published by 31 January each year and applied from the following 1 April. Since April 2023 it has had two parts for a demand site: a fixed residual charged per site per day by band, and a locational element that varies by zone.
Why has my transmission charge gone up for 2026/27?+
Because the residual grew. The revenue NESO recovers through the transmission demand residual rose from £3,836.05 million for 2025/26 to £6,265.17 million for 2026/27, and the residual is a fixed daily charge, so the increase reached every site whatever it consumed. On a 1,500 kVA high-voltage site the band rate went from £121.795409 to £185.418505 per site per day. The locational element in most southern zones actually fell over the same year.
What is a triad, and when were the last ones?+
The triad is the three half-hour settlement periods of highest net system demand between November and February, each separated from the others by at least ten clear days. The 2025/26 triads were 20 November 2025 settlement period 34, 5 January 2026 settlement period 35 and 3 February 2026 settlement period 37, published by NESO on 26 March 2026. They are always confirmed after the charging year they apply to has finished.
Can I still avoid TNUoS by cutting demand at the triad?+
Only the locational part, and in seven of the fourteen zones that part is zero for 2026/27. Before April 2023 the residual was also recovered on triad demand, so avoidance reduced both. Now the residual is a fixed daily charge that cannot be avoided by moving load. A megawatt of avoided triad demand is worth £14,130.21 a year in zone 14, South Western, £63.09 in zone 9, Eastern, and nothing at all in Scotland, the north of England, Yorkshire, north Wales and Mersey, or the East Midlands.
What is the Targeted Charging Review and what did it change?+
It is the Ofgem reform published on 21 November 2019 and updated on 18 December 2019, which decided that the residual part of network charges would be recovered as fixed charges from final demand only. For transmission that took effect in April 2023, replacing a residual recovered on triad demand with a flat charge per site per day set by band. Its purpose was to stop customers avoiding a share of fixed network costs by shifting demand rather than reducing it.
How is my TNUoS residual band decided?+
By the voltage of the connection and then by size. A site with an agreed capacity is banded on that capacity in kVA: low voltage, high voltage and extra high voltage each have four bands. A low-voltage site with no agreed capacity is banded on annual consumption instead, across the four LVN bands. Sites connected directly to the transmission system are banded on annual consumption in MWh. The distribution network operator assigns the band for a connected site, and NESO assigns it for a directly connected one.
Can I change my TNUoS band by reducing my agreed capacity?+
Not immediately. Band assignments hold for the duration of the transmission owner price control period rather than being reset each April, so a capacity reduction does not move the band at the next charging year. The routes in between are the exceptional circumstances process the distribution network operator maintains, or for a directly connected site a material change in circumstances under the code, which means a voltage change with a signed construction agreement, twelve months of metered data showing consumption more than 50% away from the figure the band was set from, or a notice to disconnect.
Do I pay TNUoS if the site consumed nothing all month?+
Yes. The residual is charged per site per day for every day the site was served, whatever it used. On a site in high-voltage band 3 that is £185.418505 a day, or £67,677.75 across the 365 days of the 2026/27 charging year, before any locational charge. Only the locational element responds to consumption, and only to demand in the three triad half hours or, on a non-half-hourly meter, to energy used between 16:00 and 19:00.
Why do two identical sites in different regions pay different TNUoS?+
Because the locational element is designed to. There are fourteen demand zones and the tariff rises the further a site sits from where generation is concentrated. For 2026/27 the half-hourly tariff is £0 per kW in zones 1 to 7 and £14.130209 per kW in zone 14, South Western. The residual is not locational, so the fixed daily part of the charge is identical wherever the site is.
When will the 2026/27 triads be published?+
At the end of March 2027, once final Elexon settlement data is available. That is after the charging year they apply to has finished, which is why suppliers bill an estimated locational charge through the year and reconcile it afterwards. Reconciliation happens twice, the second time once final settlement data is available up to sixteen months after the financial year concerned.
Does the EII exemption cover TNUoS?+
Not the exemption, but the compensation scheme alongside it does. An Energy Intensive Industries certificate removes a proportion of four policy levies and never touches network charges directly. Holding one opens the Network Charging Compensation Scheme, which refunds 90% of eligible BSUoS, DUoS and TNUoS on the certified proportion for charges incurred from 1 April 2026, up from 60% before it. The scheme pays twelve months in arrears, so the first payment at the higher rate arrives after April 2027. Only charges actually incurred and paid can be claimed.
Is TNUoS the same as DUoS?+
No. DUoS pays for the local distribution network that runs from the grid supply point to your meter, and is set by the network operator for your region under the Distribution Connection and Use of System Agreement. TNUoS pays for the national transmission network above it, is set once for the whole country by NESO under the Connection and Use of System Code, and varies by transmission zone rather than by distribution area. Most business invoices carry both.
Transmission, rebuilt from the tariff that set it.
Simplest Energy derives the zone and the band from your own meter data, prices both elements from the NESO final tariffs, and compares the result against what your supplier billed.
- TNUoS priced from the NESO published tariffs, with the TCR band derived from the meter and shown
- Locational and residual compared as separate components, so an error in one cannot be cancelled by an error in the other
- Rates held byte for byte as published, for every charging year from 2016/17 to 2026/27
- Banding a site connected directly to the transmission system, which is set on annual MWh rather than on agreed capacity
- The embedded export credit for sites exporting at a triad, whose zonal tariff is loaded but not yet priced
Built from the primary document.
Transmission Network Use of System (TNUoS) charges
Final TNUoS Tariffs for 2026/27, Report, version 1.0
Final TNUoS Tariffs for 2026/27, Tables
Final TNUoS Tariffs for 2025/26, Tables
Triads 2025/26
CUSC Section 14, Charging Methodologies, version 1.48a
Targeted charging review: decision and impact assessment
- Last reviewed
- 2 September 2026
- Technical basis
- NESO Final TNUoS Tariffs for 2026/27 v1.0 (January 2026, report and tables), CUSC Section 14 v1.48a (1 April 2026), the NESO Triads 2025/26 publication and the Ofgem Targeted Charging Review decision, all checked 2 September 2026
- Review trigger
- NESO publishing the Draft TNUoS Tariffs for 2027/28, due by 30 November 2026, or the Final Tariffs due by 31 January 2027; the 2026/27 triads, confirmed at the end of March 2027; or a concluded CUSC modification changing the demand charging methodology.
This guide explains how transmission charges are set and calculated. It is not tax, legal or procurement advice, and the rates quoted are those published for the 2026/27 charging year at the date of review, with 2025/26 shown for comparison. Check the linked source before relying on a figure.
