Skip to the content

MHHS, explained.

What Market-wide Half Hourly Settlement is, the migration timetable as published today and how far it has moved, the services and roles it replaces, and exactly which charges on a business bill it changes.

The one-minute version

What is MHHS?

Market-wide Half Hourly Settlement is the industry programme moving every electricity meter point in Great Britain onto settlement from actual half-hourly data. Until now, smaller sites have been settled against an estimated profile for their class rather than against what they really used. MHHS replaces that estimate with a measurement, for all 33 million meter points.

It is not a charge and it will not appear on your invoice as a line. What it changes is the data every time-varying charge is calculated from, and how quickly the industry finishes settling a day. Migration began on 22 October 2025 and must be complete by 7 May 2027.

Meter points to migrate
33m
Every MPAN in Great Britain moves from the legacy arrangements to the new ones, in an 18 month migration window.
Migration must be complete
7 May 2027
Milestone 15. It was October 2025 in the original 2021 decision, and has been moved twice since with Ofgem approval.
Final reconciliation, from 14
4 months
The settlement timetable shortens in two steps, for settlement days from 1 October 2026 and from 1 April 2027.

What MHHS is, and what it replaces

Electricity settlement is the process that decides how much energy each supplier bought on your behalf in each half hour, and therefore what it owes. For a site with a half-hourly meter that has always been arithmetic: the meter records a number for each of the 48 settlement periods in a day, and the number is used.

For everyone else it has been an estimate. A non-half-hourly supply carries a profile class in its meter point number, and settlement spreads a meter reading across the half hours using the average shape of everybody else in that class. Elexon defines eight: classes 1 and 2 for domestic customers, 3 and 4 for non-domestic unrestricted and Economy 7 supplies, and 5 to 8 for non-domestic maximum demand customers graded by peak load factor. BSC modification P272, implemented in April 2017, made half-hourly settlement mandatory for classes 5 to 8. Classes 3 and 4, which is most small and medium businesses in the country, have stayed on the estimate ever since.

MHHS ends that. Once a meter point has migrated it is settled from its own half-hourly data, and the profile class stops deciding anything.

The instruments it is delivered under

Ofgem decided to proceed on 20 April 2021, on the Target Operating Model produced by the industry Design Working Group, with an estimated net benefit to consumers of between £1,559 million and £4,509 million over 2021 to 2045. The codes then had to be rewritten to match. Four changes carry it:

The code changes that implement MHHS
CodeChangeStatus
Balancing and Settlement CodeP478, Implementation of Market-wide Half Hourly Settlement ArrangementsApproved by Ofgem on 26 November 2024
Retail Energy CodeR0209, Implementation of MHHS ArrangementsApproved, letter published November 2024
Distribution Connection and Use of System AgreementDCP456, MHHS Incremental Changes for Go-LiveDecided by Ofgem on 29 August 2025
Connection and Use of System CodeSection 14.17.41, the transmission charging treatment of a migrated MPANIn force in CUSC Section 14 v1.48a from 1 April 2026

The timetable as it stands today

These are the milestone dates published by the MHHS Programme and by Elexon at the date this guide was reviewed. They are not the dates the programme started with, and the section after this one says how far they have moved.

  1. 22 Sep 2025M10, central systems ready

    The Elexon central services go live and are able to accept migrating meter points. Nothing can migrate before this.

  2. 22 Oct 2025M11 and M12, migration starts

    The 18 month migration window opens, first for unmetered and advanced metered supplies, then for smart and non-smart meters.

  3. 28 Oct 2026M14, qualification deadline

    Every supplier must be qualified to operate under the new arrangements. From this point a migrated meter point cannot go back to non-half-hourly settlement on a change of supplier.

  4. 7 May 2027M15, migration ends

    All 33 million meter points are on the new arrangements. Non-half-hourly settlement stops existing.

  5. 2 Jul 2027M16, new settlement timetable

    Cutover to the shortened settlement runs, which is where the benefit the programme was justified on actually lands.

Where the migration has actually got to

Elexon reported on 17 June 2026 that more than 11.3 million migrations had completed and about a third of the metering systems in Britain were operating under half-hourly settlement, with 11 suppliers actively migrating and two suppliers about three quarters of the way through. The MHHS Programme announced on 22 July 2026 that half of industry meter points had migrated. Elexon expects around 80 per cent by October 2026.

The services it creates, and the roles it ends

MHHS is a rebuild of the central plumbing, not a tweak to it. Elexon switched on five new central systems at the readiness milestone, and three new supplier-appointed data services take over the work the old data collector and data aggregator roles did.

Created by MHHS8 new services
  • LSS, Load Shaping Service, which calculates load shapes from validated actual half-hourly data
  • MDS, Market-wide Data Service, which aggregates settlement period data for smart, non-smart, advanced and unmetered supplies
  • VAS, Volume Allocation Service, which turns that data into the volumes allocated to each supplier
  • ISD, Industry Standing Data, the reference data used in settlement under MHHS
  • DIP, Data Integration Platform, the interface participants exchange data across
  • SDS, Smart Data Service, appointed for smart and non-smart metering systems
  • ADS, Advanced Data Service, appointed for advanced metering systems
  • UMSDS, Unmetered Supplies Data Service, for unmetered supplies
Replaced or retired4 arrangements
  • Market Domain Data, the central reference data repository, replaced by Industry Standing Data
  • The Supplier Volume Allocation Agent, becomes the Volume Allocation Service, working from measured rather than profiled input
  • Profile classes as a settlement input, every migrated meter point is allocated profile class 00, the code half-hourly sites have always carried
  • Non-half-hourly settlement, once migration ends there is no meter point left whose consumption is settled from an estimate

One item on that list is not what its name suggests. The Load Shaping Service does not abolish load shapes: shapes are still needed where a smart meter has only register readings rather than settlement period data. The difference is that the shape now comes from what comparable meters actually did.

Fourteen months to four

The reason the programme was worth doing is not the data for its own sake. It is that a settlement day currently takes about 14 months to finish, and afterwards will take four. Everything reconciled inside that window reaches your invoice sooner and smaller.

The settlement runs, and when each change takes effect
RunChanges toFor settlement days from
Final Reconciliation, RFSeven months, down from 141 October 2026
Final Reconciliation, RFFour months1 April 2027
Initial Settlement, SFSeven working days, down from 151 July 2027
First Reconciliation, R129 working days1 October 2027
Post Final Settlement, DF20 months1 October 2027

Network charging moves with it. Southern Electric Power Distribution states in its 2026/27 charging statement that invoices on the aggregated approach are reconciled over approximately 14 months to reflect later and more accurate consumption figures, and that this will reduce to four months following MHHS implementation. That is the same reduction, arriving on the same charge that the DUoS guide describes in detail.

What actually changes on a business bill

Settlement volume for a non-half-hourly supply is a product of three terms. MHHS collapses the first two into one measured number and leaves the third alone.

EAC

A single annual figure for the meter point, derived from readings. It says how much, and nothing at all about when.

Profile

The coefficient that spreads that annual figure across the half hours, taken from the average behaviour of the profile class rather than from the site.

LLF

The gross-up for electricity lost as heat in the network. Unchanged by MHHS, and still applied after migration.

The third term stays. The line loss factor grosses metered volume up for the electricity lost as heat in the network, and it applies before and after migration alike.

From that one substitution the whole answer follows, and it is simpler than most coverage of MHHS makes it sound. A charge whose rate is the same in every half hour does not care what shape the volume had, because the total is the total. A charge whose rate varies by half hour cares about nothing else. Sorting the lines on a business electricity bill that way gives the whole answer.

Which charges the settlement basis actually moves
ChargeRate varies by half hourWhat migration changes
DUoS unit chargesYes, three time bandsThe split of your units across red, amber and green becomes a measurement of your site instead of the average of your profile class.
Capacity MarketYes, a window of six half hoursPeak window volume becomes your own rather than an apportionment, so the line becomes checkable for the first time.
TNUoS locationalYes, but the basis depends on the meterA current transformer metered non-domestic site moves onto the triad basis. A whole current one does not. See the worked example.
TNUoS residualNo, a fixed daily band chargeNothing. Every final demand site pays it whether it is half-hourly settled or not.
BSUoSNo, one fixed national tariff per periodNothing to the amount. The volume it applies to becomes accurate sooner.
CfD Supplier ObligationNo, one rate per MWhNothing to the amount. Reconciliation of the volume tightens with the settlement timetable.
AAHEDC and the Climate Change LevyNo, one rate per kWhNothing. Both are flat rates on total volume.

The second row is the one worth reading twice. The Capacity Market Supplier Charge is charged on demand in six half hours a day, on working days between November and February, and on nothing else. For a non-half-hourly site that figure has to be apportioned from a profile, which means the line cannot be checked against anything. After migration it is a measurement of your own site. Meanwhile BSUoS is one fixed national tariff per period and the transmission demand residual is a flat daily band charge, so neither of them moves at all.

The same site, before and after

Take a non-domestic site on the Southern Electric Power Distribution network, whole current metered, on profile class 03 today. Assume it draws 30 kW between 07:00 and 17:00 Monday to Friday and 3 kW at every other time, with no seasonal variation. The shape is the assumption and it is labelled as one. Every rate below is published for the 2026/27 charging year.

The 2026/27 charging year runs 1 April 2026 to 31 March 2027, which is 365 days, and 1 April 2026 and 31 March 2027 are both Wednesdays, so it holds 261 weekdays and 104 weekend days. Southern sets its red band at 16:30 to 19:30 on weekdays including bank holidays all year, its amber band at 07:00 to 16:30 and 19:30 to 22:00 on weekdays and 09:30 to 21:30 at weekends, and green everywhere else.

Distribution, on measured bands instead of profiled ones

Assumed demand, 07:00 to 17:00 on weekdays
30 kW
Assumed demand, every other hour
3 kW
Annual consumption that implies
96,750 kWh
Units falling in the red window, 6.07 per cent
5,872.5 kWh
Units falling in the amber window, 82.78 per cent
80,086.5 kWh
Units falling in the green window, 11.15 per cent
10,791.0 kWh
Red at 12.061p per kWh
£708.28
Amber at 1.606p per kWh
£1,286.19
Green at 0.082p per kWh
£8.85
DUoS unit charges for the year
£2,003.32

Those are the Southern Non-Domestic Aggregated Band 2 rates for 2026/27, and here is the point of the example: they are the same rates before and after migration. What changes is which of the three each unit meets. Before migration the split is the one the profile class implies. After migration it is the one above, because the meter measured it.

The sensitivity is easy to state and hard to argue with. One percentage point of this site annual consumption, 967.5 kWh, moved from the amber rate to the red rate costs 10.455p per kWh, or £101.15 a year. Whether migration raises or lowers this line depends entirely on whether the class profile overstated or understated the evening peak of this particular site, and nobody can tell you which without the data. Anyone who says MHHS will save your business money has not looked at your meter.

Transmission, where the meter type decides the answer

The site sits in TNUoS demand zone 13, Southern. For 2026/27 that zone is charged £7.354150 per kW of triad average demand on the half-hourly basis, and 1.008120p per kWh of consumption between 16:00 and 19:00 every day of the year on the non-half-hourly basis.

Units consumed 16:00 to 19:00 across the year
10,332 kWh
Non-half-hourly basis, at 1.008120p per kWh
£104.16
Demand across the triad half hours, site closed by 17:00
3 kW
Half-hourly basis, at £7.354150 per kW
£22.06
Difference, if the basis changes
£82.10

Distribution charging draws the same line in the same place. Southern receives aggregated consumption data for every migrated meter point with a whole current connection type, and site-specific data for low voltage, high voltage, extra-high voltage and unmetered connection types. Aggregated billing carries a fixed charge and three unit charges and nothing else, so migrating does not by itself bring capacity or reactive power charges to a small site.

What changes on the invoice itself

MHHS has no line of its own, so the visible evidence is in the identifiers and in the reference data behind them. These are the things that move, and each one can be checked against a document.

What migration changes on the paperwork
What you look atBefore migrationAfter migration
Profile class, the first two digits of the meter point number top line01 to 08, and it drives your charges00 for every migrated meter point, and it drives nothing
The tariff identifier in the network charging statementLine Loss Factor Class, assigned for non-migrated meter pointsDUoS Tariff ID, assigned for migrated meter points
The reference data behind the settlement combinationMarket Domain DataIndustry Standing Data
How the network operator classifies the supplyMeasurement class A to GConnection type and market segment, the segments being smart and non-smart, advanced, and unmetered
Consumption on the billActual or estimated reads spread by profileHalf-hourly data, which is what a validation of the volume needs

The first row is the one worth acting on. If the front of your meter point number still reads 03 or 04, your site has not migrated yet and every time-varying charge on the invoice is still being calculated from a class average. If it reads 00, it has.

How to check it, and what goes wrong

There is nothing to check on MHHS itself. What there is to check is the invoice either side of a migration, because a change of settlement basis mid-period is exactly the kind of event that produces a wrong bill.

  • Find the migration date. Ask your supplier when the meter point migrated. A billing period spanning it is settled on two different bases, and the invoice has to split at that date.
  • Check the profile class digit. A migrated meter point carries profile class 00. A supplier system still charging a migrated site as though it were profile class 03 is charging it on data that no longer exists.
  • Ask for the banded volumes, not the total. Once you are settled half-hourly, the network operator has your split across red, amber and green. If the invoice shows one consumption figure and one blended rate, nothing in the distribution line can be reconstructed.
  • Watch for charges that should not have appeared. Migration alone does not put a small site onto capacity and reactive power charges. Southern bills properties under transitional protection arrangements for MHHS with fixed and unit charges only, in the same manner as aggregated charges.
  • Expect reconciliations, then fewer. During the changeover the volume behind a levy can be restated more than once. After the settlement timetable cuts over, the window inside which that can happen shortens from about 14 months to four.

What is still to be decided

Two things are genuinely open, and it is worth separating them from the timetable, which is settled unless Ofgem approves another change.

The length of the migration window

Ofgem asked the programme in the CR055 decision to examine whether the 18 month migration period could be shortened, and no change has followed. What is certain is that after the supplier qualification milestone on 28 October 2026, a migrated meter point cannot return to non-half-hourly settlement on a change of supplier, so the direction of travel is one way from that date.

The shortened timetable arrives in steps, not at once

The headline is 14 months to four, and both halves are true, but they are separated by six months. The final reconciliation run drops to seven months for settlement days from 1 October 2026 and to four months for settlement days from 1 April 2027, and the initial settlement run does not compress until 1 July 2027. A reconciliation you receive in the meantime is being produced under a timetable that is itself mid-change.

Deep dives and edge cases

The main path above answers the question most businesses arrive with. These come up often enough to answer and not often enough to interrupt it.

My site is already half-hourly. Does MHHS affect me at all?Less than the coverage suggests, and not nothing.

If your site has been settled half-hourly since P272 in April 2017, the basis of your charges is not changing, because it was never an estimate. Three things still reach you. The reference data behind your tariff moves from Market Domain Data to Industry Standing Data and your Line Loss Factor Class is called a DUoS Tariff ID once you migrate. The settlement timetable shortens for everybody, so reconciliations arrive sooner. And your supplier is rebuilding the systems that produce your invoice while doing it, which is a reason to check bills through the changeover rather than after it.

Will MHHS make my bill go up?The honest answer, and why nobody can give you a different one.

For flat charges, no. BSUoS, the Contracts for Difference levy, AAHEDC and the Climate Change Levy are all one rate applied to every unit, so a more accurate view of when you used them changes nothing. What moves those amounts is a relief rather than a settlement basis: an energy intensive industries certificate removes a certified proportion of four policy levies, and it does so whether or not the meter point has migrated.

For time-varying charges it depends on your shape against the class average, and it can go either way. A business that runs office hours and closes before the evening peak has been paying for a profile that includes shops and restaurants trading into the evening, and should expect its distribution and Capacity Market exposure to fall. A business that runs into the evening has been subsidised by the same average and should expect the opposite. The programme moves cost between customers rather than creating it.

Half-hourly settlement is not the same thing as a half-hourly meterTwo words that are used interchangeably and are not the same.

A half-hourly meter is a piece of equipment that records consumption in each half hour. Half-hourly settlement is what the industry does with that data afterwards. MHHS does not require anybody to change a meter: a smart meter installed under the national rollout already records half-hourly data, and migration is a change to how that data is collected and used, not an installation programme.

The gap between the two is why the codes keep drawing their lines at whole current versus current transformer metering rather than at migrated versus not migrated. The metering equipment still determines what data exists and what can be charged from it.

What happened to the data collectors and data aggregatorsWhere the old market roles went.

The legacy arrangements split the work between a data collector, which gathered readings, and a data aggregator, which summed them for settlement, with separate appointments for half-hourly and non-half-hourly supplies. Under MHHS a supplier appoints a single data service for each market segment: a Smart Data Service for smart and non-smart metering systems, an Advanced Data Service for advanced metering systems, and an Unmetered Supplies Data Service for unmetered supplies. Aggregation itself moves to the central Market-wide Data Service.

For a business this is mostly invisible, with one exception. Metering and data charges are contractual rather than published, and the service behind them being replaced is a reasonable moment to ask what you pay for it.

Questions

What is MHHS?

MHHS stands for Market-wide Half Hourly Settlement. It is the industry programme moving every electricity meter point in Great Britain, about 33 million of them, onto settlement from actual half-hourly consumption data rather than from an estimated profile for its class. Ofgem decided to proceed on 20 April 2021 and it is delivered through changes to the Balancing and Settlement Code, the Retail Energy Code, the Distribution Connection and Use of System Agreement and the Connection and Use of System Code.

When does MHHS finish?

Migration began on 22 October 2025 and must be complete by 7 May 2027, which the programme calls milestone M15. Suppliers must be qualified to operate under the new arrangements by 28 October 2026, milestone M14. The shortened settlement timetable is cut over on 2 July 2027, milestone M16. Those are the dates published by the MHHS Programme and Elexon as at 2 September 2026.

Has the MHHS deadline been delayed?

Yes, twice, and both times with Ofgem approval. The original decision of April 2021 set a transition of four years and six months completing in October 2025. Ofgem approved change request CR022, the MHHS Programme Replan, in June 2023. Ofgem then approved change request CR055 on 29 November 2024 after systems integration testing fell behind, which moved the end of migration from October 2026 to May 2027 and the settlement timetable cutover from December 2026 to July 2027. No further Level 1 milestone change has been approved since.

What does MHHS mean for my business?

It means the charges on your bill that vary by time of day stop being calculated from the average behaviour of your profile class and start being calculated from your own consumption. That affects distribution unit charges, which are split across red, amber and green time bands, and the Capacity Market charge, which applies only to demand between 4pm and 7pm on working days from November to February. Charges that are the same rate in every half hour, such as BSUoS, the Contracts for Difference levy, AAHEDC and the Climate Change Levy, are unaffected in amount.

Will MHHS make my electricity bill go up?

It can go either way and it depends on your own demand shape against the class average. A business that closes before the early evening peak has been paying for a profile that includes premises trading into the evening, and should expect its time-banded charges to fall. A business that runs into the evening has been subsidised by the same average and should expect the opposite. MHHS moves cost between customers rather than creating it, and nobody can tell you the direction for your site without your half-hourly data.

Do I need a new meter for MHHS?

No. MHHS is not a metering installation programme. A smart meter installed under the national rollout already records consumption in each half hour, and migration changes how that data is collected, aggregated and used in settlement rather than what equipment is on the wall. Whether your meter is whole current or has a current transformer still matters, because the charging codes draw several of their rules at that boundary rather than at migration.

What happens to profile classes under MHHS?

They stop deciding anything. A migrated meter point is allocated profile class 00, the code that half-hourly metered sites have always carried, and the Southern Electric Power Distribution charging statement states that the allocation of the profile class affects charges for non-migrated meter points. Classes 1 to 8 remain in use only for the meter points that have not migrated yet, and cease to have a settlement purpose when migration ends.

How do I know if my meter point has migrated?

Look at the first two digits of the top line of the meter point administration number on your bill. That is the profile class. If it reads 03 or 04 you are a non-domestic supply that has not migrated, and your time-varying charges are still being calculated from a class average. If it reads 00 the meter point is settled half-hourly. Your supplier can also confirm the migration date, which matters because a billing period spanning it is settled on two different bases.

Does MHHS change my DUoS charges?

It changes which of the three time-banded rates each of your units meets, not the rates themselves. On the Southern Non-Domestic Aggregated Band 2 tariff for 2026/27 the red rate is 12.061p per kWh and the amber rate is 1.606p, so one percentage point of annual consumption moving between those two bands is worth 10.455p per kWh. Migration does not by itself add capacity or reactive power charges: Southern bills properties under transitional protection arrangements for MHHS with fixed and unit charges only.

Does MHHS change my TNUoS charges?

Only for some sites, and the deciding factor is the meter rather than the migration. CUSC Section 14 paragraph 14.17.41 says that a non-half-hourly metering system becoming a half-hourly one with current transformer metering at non-domestic premises is treated as Chargeable Demand Locational Capacity, the triad basis. One becoming a half-hourly metering system with whole current metering at non-domestic premises stays on Chargeable Energy Capacity, the non-half-hourly basis charged in pence per kWh consumed between 4pm and 7pm. Domestic premises also stay on Chargeable Energy Capacity. The transmission demand residual is unaffected either way.

What are the new MHHS market roles?

Elexon switched on five central systems: the Load Shaping Service, which calculates load shapes from validated actual half-hourly data, the Market-wide Data Service, which aggregates settlement period data across smart, non-smart, advanced and unmetered supplies, the Volume Allocation Service, which turns that into supplier volumes, Industry Standing Data, which replaces Market Domain Data as the central reference data, and the Data Integration Platform. Suppliers appoint a Smart Data Service, an Advanced Data Service or an Unmetered Supplies Data Service in place of the old data collector and data aggregator roles.

How long will settlement take after MHHS?

Four months instead of about 14, reached in steps. The final reconciliation run drops from 14 months to seven for settlement days from 1 October 2026 and to four months for settlement days from 1 April 2027. The initial settlement run drops from 15 working days to seven for settlement days from 1 July 2027, and the first reconciliation run and post final settlement run change for settlement days from 1 October 2027. Network charging follows: Southern states that aggregated invoices reconciled over approximately 14 months will reduce to four months following MHHS implementation.

Explanation, meet evidence.

Half-hourly data, priced against the published rate.

Once a meter point is settled half-hourly, the time-varying charges on its invoice can be rebuilt rather than trusted. Simplest Energy does exactly that.

Available now
  • Distribution unit charges rebuilt band by band from half-hourly consumption against the published windows for the network area
  • The Capacity Market rebuilt from demand in settlement periods 33 to 38 on working days from November to February
  • Line-loss factors applied to gross the metered volume up for the charges levied at the grid supply point, which are transmission, balancing and AAHEDC, and not for distribution units or the per-kWh levies
In development
  • Pricing the per-customer allocation of imbalance costs, which is contract-specific and today is held for confirmation
  • A public source for RCRC, which is not published and today comes from settlement statements

Built from the primary document.

Primary sourceOfgem, 20 April 2021

Electricity Retail Market-wide Half-hourly Settlement: Decision and Full Business Case

Primary sourceOfgem, 29 November 2024

Decision on Market-wide Half Hourly Settlement Change Request CR055, Amendments to M10 and corresponding milestones

Primary sourceOfgem, 6 June 2025

Decision to approve Market-wide Half Hourly Settlement Change Request CR061, aligning the M10 go live date to 22 September 2025

Primary sourceMHHS Programme, checked 2 September 2026

Key programme milestones, and milestone M16 cutover to the new settlement timetable

Primary sourceMHHS Programme, published 26 August 2026

Programme plan and complementary documents, plan version 6.57

Primary sourceElexon, checked 2 September 2026

Market-wide Half Hourly Settlement and the BSC

Primary sourceOfgem, 26 November 2024

Decision to approve BSC modification proposal P478

Primary sourceConnection and Use of System Code, effective 1 April 2026

CUSC Section 14, Charging Methodologies, version 1.48a, paragraph 14.17.41

Primary sourceSouthern Electric Power Distribution plc, version 1.1, 19 February 2026

Use of System Charging Statement, notice of charges effective 1 April 2026

Last reviewed
2 September 2026
Technical basis
The Ofgem MHHS decision of 20 April 2021 and the change request decisions CR022, CR055 and CR061, the MHHS Programme milestone and programme plan pages at plan version 6.57, Elexon guidance on MHHS and the BSC, CUSC Section 14 version 1.48a, and the Southern Electric Power Distribution Use of System Charging Statement version 1.1, all checked 2 September 2026
Review trigger
An Ofgem decision on a further MHHS change request moving a Level 1 milestone, the supplier qualification milestone M14 falling due on 28 October 2026, or the first step of the settlement timetable reduction taking effect for settlement days from 1 October 2026.

This guide explains an industry programme and the charges it moves. It is not tax, legal or procurement advice. The milestone dates are those published by the MHHS Programme and Ofgem at the date of review and have been revised twice already, and the rates quoted are those published for the 2026/27 charging year. Check the linked source before relying on a date or a figure.