What is the Contracts for Difference levy?
The Contracts for Difference levy, properly the CfD Supplier Obligation, is what electricity suppliers pay to fund contracts that guarantee low carbon generators a fixed price. It is charged per MWh of electricity supplied, set by the Low Carbon Contracts Company, and recovered from customers. On 2 September 2026 the rate in force is £2.068 per MWh.
It is billed twice. Suppliers pre-pay an interim rate fixed a quarter in advance, and that payment is reconciled against what generators were actually paid, day by settlement day, for ten quarterly determinations afterwards. A CfD line and a CfD reconciliation on one invoice are not a duplicate.
- Interim levy rate, per MWh
- £2.068
- In force 17 August to 30 September 2026, after an adjustment cut it from £10.559. It rises to £5.529 on 1 October.
- Reconciliation determinations
- 10
- The tenth is the final one, so a quarter closes about two and a half years after it ends.
- And 1 July, 1 October, 1 January
- 1 April
- The four dates a quarterly obligation period can start on. Every CfD figure is anchored to one.
What the levy pays for, and under what instrument
A Contract for Difference is a contract between a low carbon generator and the Low Carbon Contracts Company, a government owned counterparty, fixing a strike price for that generator. Where the market reference price is below the strike price, LCCC pays the difference. Where it is above, the generator pays money back. It is a two way settlement, a net credit to consumers in a high price year and a net cost in a low price one.
LCCC has no money of its own. The Contracts for Difference (Electricity Supplier Obligations) Regulations 2014, SI 2014/2014, oblige every licensed electricity supplier in Great Britain to fund those payments in proportion to the electricity it supplies, and that obligation is what reaches your bill. LCCC reports CfD costs of £2,216.5 million for financial year 2024/25 and £1,882.9 million for 2023/24.
Three things follow from the instrument. The rate is national, so unlike distribution charges or transmission charges it does not vary by where a site sits. It is charged on volume rather than on demand in a window, so unlike the Capacity Market charge you cannot move load to avoid it. And your supplier neither sets it nor keeps it, which puts it with the balancing charge and AAHEDC rather than with anything a contract negotiates. The guide to a business electricity bill maps where all of them sit, and the glossary has the short definition of this one.
Interim in advance, reconciled for years after
Nobody knows in July what CfD generators will be owed in July, because that depends on wholesale prices and on how much wind blew. So the regulations collect an estimate first and correct it later.
Regulation 6 requires LCCC to determine an interim levy rate for every quarterly obligation period, before the commencement of the quarterly obligation period which immediately precedes the rate period. A full quarter of notice: the rate for 1 October 2026 was determined on 16 June. Regulation 2 fixes such a period as a period of 3 months commencing after 31st March 2015 on 1st April, 1st July, 1st October or 1st January.
Alongside the rate LCCC determines a Total Reserve Amount, the reserve that lets generators be paid if the levy under collects. It is £178,346,116.46 for the current quarter, and the 12 August adjustment left it untouched while cutting the rate.
- A quarter aheadThe rate is determined→
LCCC sets the rate and the Total Reserve Amount before the previous quarter starts, and notifies every supplier with a registered BM Unit.
- During the periodSuppliers pre-pay it→
Regulation 8 charges the volume from a Balancing and Settlement Code allocation run at that rate, payable by the fifth working day after the notice.
- Mid-quarter, if neededIt can be adjusted→
An in-period adjustment changes the rate part way through the period rather than creating a new one. It happened on 17 August 2026.
- For ten quartersThen it is reconciled
Regulation 15 requires a determination in the quarter after the period, and once in every quarter after that. The tenth is final.
Ten quarterly determinations is two and a half years. That single fact answers the most common complaint about this line: a CfD adjustment for a period you settled long ago is the scheme working as written, not a supplier error. It also means changing supplier does not end your exposure to periods the old one supplied.
Who pays it, and what comes off
Everyone supplied with electricity in Great Britain pays it, at one national rate, half-hourly meter or not. What can come off is narrower than people hope.
- GB supply, Electricity supplied in Great Britain by a licensed supplier
- All meters, Half-hourly and non half-hourly points alike, at one rate
- Per MWh, Volume supplied, with no locational or time-of-day variation
- EII excluded electricity, The certified proportion of a qualifying manufacturer supply, exempt at 100 per cent of the metered electricity since the 2024 amendment, up from 85 per cent.
- Green excluded electricity, A separate exemption for renewable supply, closed on 1 April 2023, though the LCCC dataset still carries the column.
- Electricity supplied in Northern Ireland, The supplier obligation applies to supply in Great Britain.
- Gas, The scheme funds electricity generation contracts, so the levy reaches electricity bills only.
The exemption is the only route that removes a material amount. An Energy Intensive Industries certificate makes a certified share of a meter into EII excluded electricity, taken out of the calculation entirely rather than discounted, so a meter certified at 85.3 per cent pays 14.7 per cent of the levy. The EII exemption guide covers how one is obtained and why it so often fails to reach the invoice.
How the charge is calculated
At supplier level, regulation 8 makes the payment the amount of electricity supplied multiplied by the interim levy rate, on volume from a Balancing and Settlement Code allocation run. At customer level it is one of the few charges on a business invoice you can reproduce with a calculator.
The volume on the invoice, not grossed up for line losses. Other charges on the same bill are loss-adjusted; this one is not.
The rate in force for the days concerned. A bill spanning a change point is split and each part priced at its own rate.
One pound per MWh is exactly 0.1 pence per kWh, so dividing by ten moves the published rate into the unit the bill is in. Division by a power of ten is exact.
The reconciled half replaces one rate with a series: LCCC publishes a rate for every settlement day, and the true-up is each day of consumption priced at that day rate and summed. There is no shortcut through an average.
A month at the published rates
Two examples, because the levy has two halves. Both assume a flat 10,000 kWh a day, the only figure below that is not published.
The interim charge, across an in-period adjustment
August 2026 is the interesting month, because the rate changed inside it: £10.559 per MWh as determined on 17 March 2026, then £2.068 per MWh from 17 August. A bill for the whole month has to be split at that date.
- 1 to 16 August, 16 days at 10,000 kWh
- 160,000 kWh
- Priced at £10.559 per MWh
- £1,689.44
- 17 to 31 August, 15 days at 10,000 kWh
- 150,000 kWh
- Priced at £2.068 per MWh
- £310.20
- CfD line for August 2026
- £1,999.64
- The same month had the rate not been adjusted
- £3,273.29
One announcement, five days before it took effect, took £1,273.65 off one month on one site. September comes to £620.40 on the same consumption, entirely at the lower rate: about eighty per cent below July, with nothing changed at the meter.
The reconciliation, at the final daily rates
December 2024 has run its course, so final settlement run rates are published for all 31 days. The interim rate charged at the time was £8.750 per MWh. The reconciled dailies for that month run from £0.2466 on 12 December to £25.5938 on 22 December, a spread of more than a hundred times inside four weeks.
- Consumption, 31 days at 10,000 kWh
- 310,000 kWh
- Interim, at the £8.750 per MWh rate for the quarter
- £2,712.50
- Sum of the 31 final daily rates
- £322.8593
- Reconciled, each day priced at its own rate
- £3,228.59
- Effective rate over the month, derived
- £10.414816 per MWh
- Owed on reconciliation
- £516.09
The interim rate collected 84 per cent of what that month cost, and the correction arrived in instalments over the following two years. The effective rate is shown to six decimal places rather than four because it is a weighted mean of figures published at four, and such a mean is not itself known to four.
Where it appears on your invoice
There is no standard line name, and this is one of the most commonly bundled charges on a business bill. These are the forms it takes.
| Line name | What it usually means | Can it be checked |
|---|---|---|
| CfD, CFD Levy, Contracts for Difference | The supplier obligation itself, at the interim rate, per MWh or per kWh. | Yes. Rate times volume against the LCCC determination for those days. |
| Supplier Obligation, CfD Supplier Obligation | The same charge under the name the regulations use. | Yes. |
| EMR, EMR Charge, Electricity Market Reform | Usually the CfD levy and the Capacity Market charge together, sometimes with the operational costs levy folded in. | In total only. The two components have different bases and different reconciliation cycles. |
| CfD reconciliation, CfD adjustment, CfD true-up | The correction of an earlier period against the reconciled daily rates. | Yes, if the period it relates to is stated. If it is not, ask. |
| CfD Operational Costs, OCL | A separate and much smaller levy funding the running costs of LCCC itself. | Yes, against the LCCC Operational Costs Levy dataset. |
| Non-commodity, Third Party Costs, Pass-through | Every levy and network charge in one number. | No. An overcharge on one component hides under an undercharge on another. |
On a pass-through contract the levy arrives at cost and moves whenever LCCC moves it. On a fully fixed contract it sits inside the unit rate at a level the supplier guessed at, plus a premium for having guessed. Neither shape removes the cost, and only the first lets you see it.
How to check it, and what goes wrong
The CfD line is unusually checkable: the rate is national, published in advance, and applied to a volume already on the invoice. Four things go wrong often enough to name.
- The rate is the quarter, not the days. A bill spanning a change point has to be split at it. August 2026 is the live case: £10.559 to 16 August and £2.068 from 17 August. One rate across the whole month is wrong in one direction or the other.
- The volume was grossed up for losses. Several charges on the same invoice apply to loss-adjusted volume. This one does not. A line rebuilt from grossed-up kWh comes out a few per cent high, which looks like a supplier overcharge and is not.
- A certificate was missed, or over-applied. An EII exemption is applied meter by meter at the certified proportion. Under-exemption is relief paid for and not received; over-exemption is a liability to repay. Both are visible in the line.
- A reconciliation with no period on it. A true-up is only checkable if it says which obligation period it corrects. Where it does not, ask which period and which settlement run, because a reconciliation against a provisional run will itself be revised.
What is changing
The rate rises again on 1 October 2026
LCCC determined £8.176 per MWh for the quarter beginning 1 October 2026 on 16 June, then adjusted it to £5.529 per MWh on 12 August. Either way the levy more than doubles from its current level on that date, and anyone on a pass-through contract should expect the line to move on the October invoice.
A consultation on funding the obligation differently
On 13 August 2026 government opened a consultation on amending the supplier obligation so that Exchequer funding to LCCC can be reflected in the calculation, to support the British Industrial Competitiveness Scheme without raising bills for households and other non-exempt consumers. If it proceeds, the arithmetic above is unchanged and the number it runs on is not.
The exemption ceiling has already moved
The Electricity Supplier Obligations (Excluded Electricity) (Amendment) Regulations 2024 raised the exemption for EII excluded electricity from 85 per cent of the electricity measured by the meter to 100 per cent. A certificate is worth more against this levy than it was, so any invoice still applying the older ceiling is worth a look.
Deep dives and edge cases
The main path covers the levy as it reaches most bills. These come up often enough to answer, and not often enough to interrupt it.
Why the interim rate cannot go below zeroWhat happens when generators are paying money back.+
Through the 2021 and 2022 price spike the reference price sat above most strike prices, so CfD generators were net payers into the scheme. The reconciled daily rate went firmly negative: 8 March 2022 settled at minus £22.6829 per MWh, and 1,620 rows in the dataset are negative.
The interim rate did not follow, because it cannot. LCCC has stated that the regulations governing its levy powers do not allow it to set an ILR of less than zero, and the rate was held at £0 per MWh from September 2021. The money reached suppliers through the quarterly reconciliation instead, months late and as an adjustment rather than as a lower rate.
Settlement runs, and which rate is the real oneII, SF, R1, R2, R3, RF and DF, and why the latest is not always the answer.+
A settlement day is restated several times as better metering data arrives, and LCCC publishes a reconciled rate for each run. The early II and SF runs often carry no rate at all, and a blank there is not a zero: that run produced no figure, and it must never be priced as free.
The runs do not arrive in a tidy order either. On 15 January 2024 the published rates are £9.8373 at R1, £9.8602 at R2, £9.8621 at R3, £9.4400 at RF and £9.4717 at DF. The right figure is the DF one, because DF outranks RF, not because it was published last. Precedence rather than recency is the difference between a right answer and a plausible one.
The operational costs levy is a different chargeA second CfD line, funding LCCC rather than generators.+
LCCC recovers its own running costs through a separate levy, published per MWh for a financial year rather than a quarter. For 1 April 2026 to 31 March 2027 it is £0.1463 per MWh, from a forecast budget of £38.274 million over forecast demand of 261.55 TWh, rising to £0.1714 for 2027/28 and £0.1900 for 2028/29.
It is worth naming, because a supplier that folds it into the CfD line makes both figures unreconcilable. Unlike the supplier obligation it carries an actuals column and a refund rate, so an over recovery is returned rather than reconciled.
What happens if another supplier defaultsMutualisation, and why a levy you have already paid can come back.+
Under regulation 17, where a supplier fails to make a relevant payment and LCCC holds no collateral from it, LCCC may require the non-defaulting suppliers to pay a share of the shortfall, apportioned by the volume each supplied over the most recent period of 30 consecutive days for which allocation data exists. Regulation 18 requires repayment if the money is later recovered. So an unexplained movement in a levy line is not always about your own supply.
Questions
What is the CfD charge on my electricity bill?+
It is the Contracts for Difference Supplier Obligation levy. Contracts for Difference guarantee low carbon generators a fixed price for their output, and where the market reference price sits below that strike price the Low Carbon Contracts Company pays generators the difference. Every licensed electricity supplier in Great Britain funds that in proportion to the electricity it supplies, under the Contracts for Difference (Electricity Supplier Obligations) Regulations 2014. Suppliers recover it from customers, which is why it appears on business bills as a rate per MWh of electricity supplied.
What is the interim levy rate right now?+
£2.068 per MWh. LCCC determined the rate for the quarterly obligation period 1 July 2026 to 30 September 2026 at £10.559 per MWh on 17 March 2026, then made an in-period adjustment on 12 August 2026 cutting it to £2.068 per MWh for the shortened period 17 August 2026 to 30 September 2026. The Total Reserve Amount of £178,346,116.46 was left unchanged. LCCC gave elevated market prices as the reason, and the rate rises to £5.529 per MWh on 1 October 2026.
How is the interim levy rate set, and how much notice is there?+
Regulation 6 of the Contracts for Difference (Electricity Supplier Obligations) Regulations 2014 requires the CFD counterparty to determine an interim levy rate in respect of every quarterly obligation period, before the commencement of the quarterly obligation period which immediately precedes the rate period. That is a full quarter of notice: the rate for 1 October 2026 was determined on 16 June 2026, two weeks before the July quarter had even begun. LCCC must then publish a notice as soon as reasonably practicable and issue it to every supplier with a registered BM Unit.
What is a quarterly obligation period?+
Regulation 2 defines it as a period of 3 months commencing after 31st March 2015 on 1st April, 1st July, 1st October or 1st January. Every CfD levy figure is anchored to one of those four dates. An in-period adjustment does not create a new obligation period, it changes the rate part way through the existing one, which is why the notice for the current adjustment describes its period as 17 August 2026 to 30 September 2026.
Why has a CfD reconciliation appeared on a bill for a period I already paid for?+
Because the interim rate is a forecast and the real cost is only known afterwards. Regulation 15 requires a reconciliation determination before the conclusion of the quarterly obligation period which immediately follows the reconciliation period, and then once in every subsequent quarterly obligation period, and paragraph (2) makes the final reconciliation determination the tenth one. Ten quarterly determinations is two and a half years, so a CfD adjustment landing on a bill long after the period it relates to is the scheme working as written rather than a supplier error.
What is the reconciled daily levy rate?+
It is the result of the reconciliations of the daily CfD payments divided by the daily eligible demand, published by LCCC as its Reconciled Daily Levy Rates dataset. The figure for one settlement day is restated as settlement runs progress from II and SF through R1, R2 and R3 to RF and DF. For 11 December 2024 the RF run gives £0.9605 per MWh, against the £8.750 per MWh interim rate actually charged for that quarter. The daily rate is what the interim rate is eventually trued up against.
Can the CfD levy be negative?+
The daily reconciled rate can be, and often is. When the market reference price is above the strike price, generators pay money back to LCCC and the scheme is a net credit for that day. The reconciled rate for 8 March 2022 is minus £22.6829 per MWh on the RF run, and 1,620 of the rows in the published dataset are negative. The interim levy rate cannot be negative. LCCC has stated that the regulations governing its levy powers do not allow it to set an ILR of less than zero, so the rate sat at £0 per MWh from September 2021 and the money went back to suppliers through the quarterly reconciliation instead.
Is the CfD levy charged on metered kWh or on grossed-up volume?+
Suppliers bill customers on metered consumption. Regulation 8 sets the supplier level payment as the amount of electricity supplied multiplied by the interim levy rate, taken from a Balancing and Settlement Code volume allocation run, so the supplier is exposed to settled volume rather than to the meter. In practice the levy reaches a customer as a rate per MWh applied to the kWh on the invoice, with no line loss factor applied. A rebuild that grosses the volume up for losses will come out too high.
Does an EII certificate remove the CfD levy?+
It removes the certified proportion of it. Contracts for Difference is one of the four schemes an Energy Intensive Industries certificate exempts, and the electricity concerned becomes EII excluded electricity, taken out of the supplier obligation calculation entirely. The Electricity Supplier Obligations (Excluded Electricity) (Amendment) Regulations 2024 increased the level of exemption for EII excluded electricity from 85 per cent of the electricity measured by the meter to 100 per cent. A meter certified at 85.3 per cent therefore pays 14.7 per cent of the levy.
What is the CfD operational costs levy, and is it the same charge?+
No, it is a second and far smaller line. The operational costs levy funds the running costs of the Low Carbon Contracts Company itself rather than payments to generators. LCCC publishes the rate in its Operational Costs Levy dataset: £0.1463 per MWh for 1 April 2026 to 31 March 2027, from a forecast budget of £38.274 million over forecast demand of 261.55 TWh. That is about one fourteenth of the supplier obligation rate in force today, and about one thirty-eighth of the rate that applies from 1 October 2026.
Why did my CfD line fall in August 2026 when my usage did not change?+
Because the rate changed part way through the month. The interim levy rate for 1 to 16 August 2026 was £10.559 per MWh and from 17 August it was £2.068 per MWh. A bill covering the whole of August has to be split at that date and each part priced at the rate in force, and a bill for September falls entirely at the lower rate. Comparing a September invoice against a July one on identical consumption will show the levy line down by about eighty per cent for that reason alone.
How much does the Contracts for Difference scheme cost in total?+
LCCC reports CfD costs of £2,216.5 million for financial year 2024/25 and £1,882.9 million for 2023/24 on its supplier and shipper resources page. Those are the amounts recovered from electricity suppliers across Great Britain, and they are what the interim levy rate and the ten quarterly reconciliations after it are collecting.
The levy, rebuilt from the rate that was in force.
Simplest Energy prices the CfD line from the LCCC determinations and the published daily rates, then compares it against what your supplier billed.
- The supplier obligation priced from the published interim levy rate history, split at every change point
- Reconciled true-ups priced day by day, resolved by settlement run precedence
- EII exemption applied at the certified proportion before the line rounds to pence
- The CfD operational costs levy checked against the contract rate, which is the only per-customer source there is, because no per-customer schedule is published
- Reconciled true-ups on a supply that is not fully half-hourly, or on a day that has not reached a final settlement run, which are held rather than firmed
Built from the primary document.
The Contracts for Difference (Electricity Supplier Obligations) Regulations 2014
LCCC determines ILR and TRA for 2026 Q3, posted 17 March 2026
LCCC determines ILR and TRA for 2026 Q3 in-period adjustment effective from 17 August 2026, posted 12 August 2026
Supplier and shipper resources, scheme costs by financial year
LCCC determines ILR and TRA for 2026 Q4, posted 16 June 2026
Reconciled Daily Levy Rates, dataset last updated 10 July 2026
Operational Costs Levy, dataset last updated 1 April 2026
Moving the money
The Electricity Supplier Obligations (Excluded Electricity) (Amendment) Regulations 2024, explanatory note
- Last reviewed
- 2 September 2026
- Technical basis
- The Contracts for Difference (Electricity Supplier Obligations) Regulations 2014, the LCCC determinations for 2026 Q3 and 2026 Q4 and the in-period adjustment effective 17 August 2026, and the LCCC Reconciled Daily Levy Rates and Operational Costs Levy datasets, all checked 2 September 2026
- Review trigger
- A new LCCC determination or an in-period adjustment to the Interim Levy Rate, the start of the 1 October 2026 obligation period at £5.529 per MWh, or the outcome of the consultation opened on 13 August 2026 on amending the supplier obligation for the British Industrial Competitiveness Scheme.
This guide explains how the CfD supplier obligation is set and calculated. It is not tax, legal or procurement advice. The interim levy rate can be adjusted part way through a quarter, and was on 12 August 2026, so check the current LCCC notice before relying on a rate.
